Background notes
295 short notes from September 2026 on grid operators’ project pages and on neighbouring countries. They are not tied to a project in the register, so they are not counted as news.
- Ellevio’s Högberga page is an autumn-2026 station rebuild, not reserved Lidingö hall power
- Ellevio’s Beckomberga page is a 2026 outdoor-station rebuild, not reserved west-Stockholm hall power
- Ellevio’s Yellow-line page is an autumn-2026 TBM feeder, not reserved Älvsjö hall power
- Fingrid’s Nuojuankangas–Seitenoikea page is a 2026 field-study window, not reserved Kainuu hall power
- Statnett’s 12 August Refsdal–Modalen note is a monomast hearing, not reserved Bergen-area hall power
- Statnett’s Samnanger–Øygarden page is a 26 June southern-route hearing, not reserved Øygarden hall power
- Statnett’s 11 June Flesaker–Hof–Tveiten note is a 300-to-420 kV filing, not reserved Vestfold hall power
- Fingrid’s March Juurikkaperä–Toivila note is a reasoned conclusion, not reserved Jämsä hall power
- Ellevio’s Otterbäcken page is an April-2026 paper-mill feeder, not reserved Gullspång hall power
- Vattenfall’s Kolbotten–Nynäshamn page is a Q1-2026 detail-design start, not reserved Södertörn hall power
- Fingrid’s Hausjärvi–Anttila page is a 2026 field-study year, not reserved east-Uusimaa hall power
- Vattenfall’s 16 September Lindome–Skalmered note is a filed 130 kV concession, not reserved Härryda hall power
- Vattenfall’s Överby–Kungsängen page is an open 2026 scoping consult, not reserved Upplands-Bro hall power
- Ellevio’s Älvdalen–Väsa page is a 2025–2026 rebuild, not reserved Dalarna hall power
- Vattenfall’s Färlev–Tossene page is a 130 kV build under way, not reserved Sotenäs hall power
- Vattenfall’s Lextorp–Lunden page is an autumn-2026 construction start, not reserved Trollhättan hall power
- Fingrid’s Aurora Line 2 page is a 2026 grid study, not reserved northern-Sweden hall power
- Statnett’s Lillehammer–Gran page is a 2026 Oslo-melding plan, not reserved Innlandet hall power
- Vattenfall’s May Minninge–Stigtomta note is a solar-and-Ostlänken design year, not reserved Nyköping hall power
- Fingrid’s Isohaara–Taivalkoski page is a 2026 general-design year, not reserved Keminmaa hall power
- Vattenfall’s Ullna–Täljö page is a spring-2026 rebuild-finish plan, not reserved Österåker hall power
- Statnett’s 20 March Lebesby–Seidafjellet note is a joint progress plan, not reserved Varangerbotn hall power
- Ellevio’s Tigerberget–Enån paper is a November 2025 wind-tie consult, not reserved Ljusdal hall power
- Ellevio’s July Repbäcken–Alvik paper is a complementary station-site consult, not reserved Falun hall power
- Ellevio’s Borgvik–Backa page is a post-summer 2026 consult plan, not reserved Årjäng hall power
- Ellevio’s Fjärås–Väröbacka page is an autumn-2026 rebuild start, not reserved Halland hall power
- Statnett’s 19 June Blåfalli–Gismarvik note is a summer works list, not reserved Haugaland hall power
- Vattenfall’s late-April Ed–Östhammar–Harg note is a 70-to-130 kV route choice, not reserved Östhammar hall power
- Vattenfall’s 20 April Uddebo–Lockryd note is a closed 130 kV consult, not reserved Svenljunga hall power
- Vattenfall’s 9 April Silverdal–Edsberg note is a Danderydsvägen works start, not reserved Sollentuna hall power
- Fingrid’s Huutokoski–Kontiolahti page is a 2026 EIA and landowner-letter window, not reserved North Karelia hall power
- Fingrid’s March Hikiä–Inkoo note is a reasoned conclusion and route choice, not reserved west-Uusimaa hall power
- Vattenfall’s 31 January Flemingsberg note is a water-operations consult, not reserved Huddinge hall power
- Fingrid’s Lieto–Raisio page is a 2026 EIA report stage, not reserved Turku-region hall power
- Fingrid’s Huittinen–Forssa page is a printed autumn-2025 works finish, not reserved Satakunta hall power
- Fingrid’s 8 November Petäjäskoski–Herva note is an expropriation and a delay, not reserved Lapland hall power
- Ellevio’s Lindbacka page is an autumn-2026 consult plan, not reserved Örebro hall power
- Fingrid’s Kristinestad–Nokia page is 2026 general design, not reserved west-coast hall power
- Vattenfall’s Krylbo–Igeltjärna note is an Ei remittal, not reserved Avesta hall power
- Fingrid’s 18 February Anttila–Länsisalmi note is a reasoned conclusion, not reserved capital-region hall power
- Statnett’s 10 February Sauda–Gismarvik note is an NVE investigation programme, not reserved Haugaland hall power
- Ellevio’s February Sälen–Idre note is an appealed regional permit, not reserved mountain-hall power
- Statnett’s 2026 Hamang–Bærum–Smestad note is a full-tunnel review, not reserved Greater Oslo hall power
- Fingrid’s Metsälinja reinforcement page is 2026 field work, not reserved central-Finland hall power
- Vattenfall’s 31 October Måby–Hagby note is a new-concession consult, not reserved north-Stockholm hall power
- Svenska kraftnät’s 11 September Tuna note is an Uppsala-station in-service day, not reserved hall megawatts
- Ellevio’s 29 August Blyberg–Grönklitt note is a complementary consult, not reserved Dalarna hall power
- Fingrid’s 7 November Herva–Nuojuankangas note is an expropriation and construction start, not reserved northern hall power
- Vattenfall’s Gävle–Sandviken 8 September note is commissioning and restoration, not live hall megawatts
- Fingrid’s Seinäjoki–Hirvisuo page is an EIA report and hearing notice, not reserved Ostrobothnia hall power
- Vattenfall’s August Hjortsberga note is a cancelled industrial offtake, not reserved Eskilstuna hall power
- NVE’s Vik case page is a station concession under appeal, not a granted Vik–Ramnaberg line or reserved Bergen hall power
- Vattenfall’s 1 June Hedenlunda–Oxelösund note is withdrawn steel-mill appeals, not reserved SE3 hall power
- Elering’s 26 April EstLink 2 note is a converter cooling fault, not EstLink 3 and not reserved hall power
- Vattenfall’s 21 April Litslena–Bålsta page is a filing awaiting remittal, not reserved Mälaren hall power
- Statnett’s 7 April Liåsen note is a southern-Oslo construction update, not reserved Oslo hall power
- Ellevio’s Torslanda–Björkö paper is a 52 kV archipelago consultation, not reserved Gothenburg hall power
- Fingrid’s Harjulinja note is an EIA-programme opinion, not reserved central-Finland hall power
- Svenska kraftnät’s 10 February NordBalt note is existing-HVDC support, not new reserved SE4 hall power
- Ellevio’s Laforsen–Enån paper is a short hydropower station-tie consultation, not the 400 kV Enån corridor and not reserved hall power