Published 2026-09-12 · Event 2026-09-01
Ellevio’s Lindbacka page is an autumn-2026 consult plan, not reserved Örebro hall power

Ellevio’s Lindbacka project page writes a concession investigation now and a consultation with landowners planned for autumn 2026, with construction late 2028. A planned consult is not reserved offtake.
Ellevio’s Lindbacka project page is the dated planning source used here. It writes that the present transmission station at Lindbacka in Örebro Municipality is a hub for distributing electricity in Närke and eastern Värmland, and that the station has reached the end of its technical life. Ellevio plans to replace it with a new station 500 metres from today’s site and to move the existing regional lines onto the new station. Construction is written as starting in late 2028. A station-replacement plan is not reserved hall offtake.
The consult sentence must stay a consult sentence. The page writes that a concession investigation is under way now, and that Ellevio plans to consult affected landowners, authorities and other parties in autumn 2026. The consultation is written as covering the line move. Those who are affected are to be told when the consult starts and how to comment. A planned autumn consult is not a construction start and not a reserved megawatt.
The distance-and-purpose sentence must stay a distance-and-purpose sentence. Five hundred metres between the old station and the new one, and a move of regional lines, are works facts. The page does not give a megawatt, a customer or a hall. Those missing figures stay missing.
Related grid notes stay on their own pages. Other Örebro regional-grid rows and later concession filings are different dates and different instruments. This article does not import a reserved hall offtake or a construction start into an autumn-2026 consult plan.
DataCenterSweden records autumn 2026 as an Ellevio concession-investigation and planned-consult notice for Lindbacka. No project identifier is attached. The next update would need a later primary source that names the consult as opened, a filed concession, construction under way in late 2028, or a reserved consumption agreement with a printed megawatt. Until then, the planned consult stays a station-replacement paper — not reserved Örebro hall capacity.
Why it matters
A transmission-station rebuild in Örebro is easy to file as spare hall power. The page is usable only if the autumn consult stays a consult — not a reservation.
What remains unknown
The page does not open the autumn 2026 consult, start late-2028 construction or give a reserved hall megawatt beside Lindbacka.
Sources
- Rebuild of the station and lines at Lindbacka (Örebro) — Ellevio (publication date not stated). Checked 2026-09-12.