Published 2026-09-12 · Event 2026-03-21

Vattenfall’s Ullna–Täljö page is a spring-2026 rebuild-finish plan, not reserved Österåker hall power

Construction cranes above a generic industrial building site.
Photo Sergej Karpow on Unsplash

Vattenfall Eldistribution’s Ullna–Täljö page writes that 70-to-130 kV rebuild works have run since late summer 2025 and are planned ready by spring 2026. A planned finish is not reserved offtake.

Vattenfall Eldistribution’s Ullna–Täljö project page is the dated rebuild source used here. It writes a conversion of the regional grid from 70 kV to 130 kV between Ullna and Täljö. A consult is written as autumn 2019 and a line-concession application as March 2021. Line measures are written as affecting Täby, Vallentuna and Österåker. A 70-to-130 kV conversion page is not reserved hall offtake.

The station sentence must stay a station sentence. Beside the stretch reinforcement the page writes a new 130 kV distribution station at Täljö, with a short underground-cable stretch between the existing and the new transformer station. Those are station facts. They are not a reserved megawatt.

The works sentence must stay a works sentence. The project is written as having started in 2024, with rebuilds on the affected stretch under way since late summer 2025 and now approaching their end. Late autumn is written as difficult: hard frost in early November, then heavy rain, thaw and tracked ground after vehicles. Restoration of forest and land is written as ongoing. The project is written as planned ready by spring 2026. A spring-2026 finish plan is not a named hall.

Related grid notes stay on their own pages. Other north-east Stockholm regional-grid rows are different dates and different stretches. This article does not import a reserved hall offtake into a printed spring-2026 finish window.

DataCenterSweden records spring 2026 as a Vattenfall planned rebuild-finish window for Ullna–Täljö. No project identifier is attached. The next update would need a later primary source that names the 130 kV stretch or the Täljö station as in service, or a reserved consumption agreement with a printed megawatt. Until then, the spring window stays a conversion paper — not reserved Österåker hall capacity.

Why it matters

A north-east Stockholm 130 kV headline is easy to file as spare hall power. The page is usable only if the spring-2026 finish stays a printed plan — not a reservation.

What remains unknown

The page does not name the spring-2026 finish as done or give a reserved hall megawatt beside Ullna–Täljö.

Sources

  1. Ullna–Täljö 70-to-130 kV — rebuild toward spring 2026 Vattenfall Eldistribution (publication date not stated). Checked 2026-09-12.