Published 2026-09-12 · Event 2026-09-01
Vattenfall’s Färlev–Tossene page is a 130 kV build under way, not reserved Sotenäs hall power

Vattenfall Eldistribution’s Färlev–Tossene page writes that construction of a new 130 kV line and a new Tossene station is under way between Munkedal, Lysekil and Kungshamn. Works under way are not reserved offtake.
Vattenfall Eldistribution’s Färlev–Tossene project page is the dated works source used here. It writes a new 130 kV line on the Färlev–Tossene stretch, between Munkedal, Lysekil and Kungshamn, plus a new transformer station at Tossene. The project is written as meeting development and need in the Sotenäs/Lysekil area and its coastal communities, and as securing a robust supply. A coastal 130 kV build is not reserved hall offtake.
The works sentence must stay a works sentence. Construction of the line is written as under way. The hilly terrain is written as meaning that many different pole types are needed along the stretch. Those are construction facts. They are not a reserved megawatt and not a printed finish month.
The station sentence must stay a station sentence. At Tossene the page writes a wholly new transformer station with 130, 40 and 10 kV switchgear. That station is written as replacing the existing 40/10 kV station from the 1970s and as adding a wholly new voltage level in the area in order to increase capacity. A new voltage level is not a named hall.
Related grid notes stay on their own pages. Vattenfall’s Uddebo–Lockryd consult row and other Västra Götaland regional-grid papers are different dates and different stretches. This article does not invent a finish half-year, a tenant or a reserved hall offtake into a page that only writes works under way.
DataCenterSweden records the current Färlev–Tossene page as a Vattenfall works-under-way notice. No project identifier is attached. The next update would need a later primary source that names the line or the Tossene station as in service, or a reserved consumption agreement with a printed megawatt. Until then, the build stays a Bohuslän regional-line paper — not reserved Sotenäs hall capacity.
Why it matters
A new 130 kV Bohuslän headline is easy to file as spare coastal hall power. The page is usable only if works under way stay works — not a reservation.
What remains unknown
The page does not print a finish month, name Tossene as in service or give a reserved hall megawatt beside Färlev–Tossene.
Sources
- Färlev–Tossene 130 kV and new Tossene station — works under way — Vattenfall Eldistribution (publication date not stated). Checked 2026-09-12.