Published 2026-09-12 · Event 2026-02-01

Ellevio’s February Sälen–Idre note is an appealed regional permit, not reserved mountain-hall power

An industrial interior with equipment carts and overhead pipework.
Photo Lawrence Krowdeed on Unsplash

Ellevio’s Sälen–Idre page writes that the Energy Markets Inspectorate granted a permit in February 2026 to build the regional line, and that the decision has been appealed. An appealed permit is not reserved offtake.

Ellevio’s Sälen–Idre project page is the dated permit source used here. It writes that the grid up to the Idre area is under-dimensioned and needs to be expanded for growing mountain tourism. Ellevio has applied to build an eight-Swedish-mile regional line from Sälen up to Idre, where a new regional station is planned. In February 2026 Ellevio received a permit from the Energy Markets Inspectorate to build the line. A tourism-grid permit is not reserved hall offtake.

The appeal sentence must stay an appeal sentence. The same paragraph writes that the decision has been appealed. The page does not name the appellant or print a court outcome. An appealed Inspectorate permit is not a concession in undisturbed legal force and not a reserved megawatt.

The consult sentence must stay a consult sentence. Ellevio carried out consultation in spring 2023 before the permit application. After comments from property owners and Idre sameby, Ellevio examined the proposed alternative and held a complementary consultation in autumn 2023. Those are process facts. They are not a construction start.

Related grid notes stay on their own pages. Ellevio’s Blyberg–Grönklitt–Våmhus complementary-consult note and other Dalarna regional-grid rows are different dates and different stretches. This article does not import a ski-area 50 kV consult, or a reserved hall offtake, into a February appealed permit.

DataCenterSweden records February 2026 as an Ellevio appealed-permit notice for Sälen–Idre. No project identifier is attached. The next update would need a later primary source that names the appeal outcome, a permit in legal force, construction under way, or a reserved consumption agreement beside the eight Swedish miles. Until then, the February permit stays an appealed regional-grid paper — not reserved mountain-hall capacity.

Why it matters

An eight-Swedish-mile regional line into Idre is easy to file as spare mountain hall power. The February note is usable only if the appealed permit stays an appealed permit — not a reservation.

What remains unknown

The page does not name the appellant, print the appeal outcome or name a reserved hall offtake beside the planned Idre station.

Sources

  1. Planned regional line between Sälen and Idre Ellevio (publication date not stated). Checked 2026-09-12.