Ellevio’s Otterbäcken page is an April-2026 paper-mill feeder, not reserved Gullspång hall power

An industrial interior with equipment carts and overhead pipework.
Photo Lawrence Krowdeed on Unsplash

Ellevio’s Otterbäcken project page writes an April 2026 start and an end-2027 finish for a new outdoor station and a ground cable to Vajda Papir’s mill switchgear. A named mill feeder is not reserved hall offtake.

Ellevio’s Otterbäcken industrial-connection page is the dated feeder source used here. It writes that Ellevio is strengthening regional- and local-grid capacity so that Vajda Papir’s paper mill can establish itself in Otterbäcken. A new outdoor station is written as supplying the mill’s production, with a ground cable from that station to the mill’s switchgear. A named mill feeder is not reserved hall offtake.

The timetable sentence must stay a timetable sentence. The start is written as April 2026 and the planned finish as the end of 2027. The connection is written as three stages. The page does not print what those three stages are. This article does not invent the missing stage list. A three-stage mill sentence without a megawatt is not a reserved hall.

The works sentence must stay a works sentence. The page writes that the work may mean noise and heavy traffic in the area, and that planned outages may occur, to be announced in good time by text or letter. Those are traffic-and-outage facts. They are not a campus agreement.

Related grid notes stay on their own pages. Ellevio’s Skaraborg connection snapshot already on this site, Vattenfall’s Lextorp–Lunden row and other Västra Götaland regional-grid papers are different dates and different instruments. This article does not import a reserved hall offtake, or invent a printed megawatt, into an April-2026 mill feeder.

DataCenterSweden records April 2026 as an Ellevio mill-feeder start for Otterbäcken. No project identifier is attached. The next update would need a later primary source that names the end-2027 connection as finished, or a reserved consumption agreement that prints a megawatt for a hall. Until then, the April start stays a paper-mill feeder — not reserved Gullspång hall capacity.

Why it matters

A named industrial-connection headline is easy to file as spare hall power. The page is usable only if Vajda Papir stays a mill — not a hall reservation.

What remains unknown

The page does not list the three stages, finish the end-2027 connection or give a reserved hall megawatt beside Otterbäcken.