Ellevio’s 29 August Blyberg–Grönklitt note is a complementary consult, not reserved Dalarna hall power

An industrial interior with equipment carts and overhead pipework.
Photo Lawrence Krowdeed on Unsplash

Ellevio’s current-consultations page set 29 August 2025 as the complementary deadline for two new 50 kV lines between Blyberg, a new Grönklitt station and Våmhus. A complementary deadline is not reserved offtake.

Ellevio’s current-consultations page, with the January 2025 consultation paper beside it, is the dated complementary-consult source used here. The January paper writes two new 50 kV overhead lines in Mora, Orsa and Älvdalen municipalities, Dalarna County: Blyberg–Grönklitt about 24 kilometres and Grönklitt–Våmhus about 10 kilometres, about 34 kilometres in total. The complementary row on the consultations page names the same stretch and sets 29 August 2025 as the last reply day. A complementary deadline is not reserved hall offtake.

The purpose sentence must stay a purpose sentence. The January paper writes strong demand for larger new connections in the area, including from ski facilities, new housing and charging infrastructure. The local network is written as unable to take those new connections and as needing relief, while backup supply also needs to be strengthened. A new Grönklitt station is written as placed in an old quarry so as to limit land take. Those are ski-and-housing grid facts. They are not a reserved hall megawatt.

The filing sentence must stay a filing sentence. The January paper writes that the concession application was planned for the fourth quarter of 2025. That planned quarter stays a planned quarter on a January paper. This article does not invent a later filing date. The first consult’s last reply day was written as 18 March 2025; the complementary deadline is the 29 August 2025 row.

Related grid notes stay on their own pages. Ellevio’s Sälen–Idre appealed-permit note and the Laforsen–Enån consultation paper are different dates and different stretches. This article does not import an eight-Swedish-mile mountain permit, or a reserved hall offtake, into a 29 August complementary 50 kV deadline.

DataCenterSweden records 29 August 2025 as an Ellevio complementary-consult deadline for Blyberg–Grönklitt–Våmhus. No project identifier is attached. The next update would need a later primary source that names the concession application as sent, an Inspectorate decision, or a reserved consumption agreement beside the 34 kilometres. Until then, the August deadline stays a ski-area regional-grid paper — not reserved Dalarna hall capacity.

Why it matters

A 34-kilometre 50 kV headline into Grönklitt is easy to file as spare Dalarna hall power. The 29 August row is usable only if the complementary consult stays a consult — not a reservation.

What remains unknown

The pages do not print the concession application as sent, an Inspectorate decision or a reserved hall offtake beside the new Grönklitt station.