Published 2026-09-12 · Event 2025-09-15

Vattenfall’s 16 September Lindome–Skalmered note is a filed 130 kV concession, not reserved Härryda hall power

Utility transformers and a web of overhead power lines against a clear sky.
Photo Alivia Alva on Unsplash

On 16 September 2025 Vattenfall Eldistribution said the Lindome–Skalmered concession had been filed with the Inspectorate on 15 September. A filed concession is not reserved offtake.

Vattenfall Eldistribution’s Lindome–Skalmered page is the dated filing source used here. It writes a new 130 kV overhead line from the Vattenfall station outside Lindome in Mölndal toward a planned new station east of Skalmered in Härryda Municipality. The existing Lindome station is written as being reinvested and moved slightly north. The stretch is written as running mainly parallel to Svenska kraftnät’s existing 400 kV line, with shorter stretches in a new corridor. A 130 kV infeed filing is not reserved hall offtake.

The purpose sentence must stay a purpose sentence. Härryda Municipality is written as wanting increased delivery from Vattenfall. The page writes a new infeed point into Härryda Energi’s grid, to strengthen today’s supply and to size the grid for sustainable municipal development. Those sentences stay the page’s own wording. They do not name a hall and do not print a megawatt.

The process sentence must stay a process sentence. A complementary consult opened on 4 February 2025, with comments through 7 March 2025, is written as covering a new pole type on part of the stretch, a new partial alignment, an extended cable stretch and adjusted connections at the Lindome and Skalmered stations. The 16 September 2025 line says comments have been weighed, a preferred alignment chosen, and the concession filed with the Inspectorate on 15 September. The page writes that it is waiting for the Inspectorate. A waiting sentence is not a concession in legal force.

Related grid notes stay on their own pages. Vattenfall’s Göteborg–Rosbacka concession row and the Cederslund–Perstorp consult already on this site are different dates and different stretches. This article does not import a reserved hall offtake into a 15 September 2025 Lindome–Skalmered filing.

DataCenterSweden records 15 September 2025 as a Vattenfall Eldistribution concession filing for Lindome–Skalmered. No project identifier is attached. The next update would need a later primary source that names an Inspectorate decision, construction under way, or a reserved consumption agreement with a printed megawatt. Until then, the September filing stays a 130 kV infeed paper — not reserved Härryda hall capacity.

Why it matters

A filed 130 kV concession toward Härryda is easy to file as spare west-coast hall power. The page is usable only if the 15 September filing stays a filing — not a reservation.

What remains unknown

The page does not print an Inspectorate decision, start construction or name a reserved hall offtake with a printed megawatt beside Lindome–Skalmered.

Sources

  1. Lindome–Skalmered 130 kV — concession filed 15 September 2025 Vattenfall Eldistribution, 2025-09-16. Checked 2026-09-12.