Upcoming decisions for Swedish data centers

Council votes, deadlines, construction starts and commissioning dates that lie ahead. Every item has a source that states the date. Companies’ own targets and dates we have calculated ourselves are labelled.

2026

  1. 16 November 2026

    In 3 days

    Scheduled

    Political decision · Sundsvall municipal executive committee

    Almåsen detailed plan goes to Sundsvall’s executive committee

    The urban planning committee proposed adoption on 21 October 2026. According to SVT the plan is handled by the executive committee on 16 November before the council decides.

    Verda AI centre, Sundsvall (Almåsen) →Source: SVT Nyheter Västernorrland

  2. 30 November 2026

    In 17 days

    Scheduled

    Political decision · Sundsvall municipal council

    Sundsvall council decides on the Almåsen detailed plan

    The municipality’s project page gives 30 November 2026 for adoption of the plan for the industrial area where Verda plans an AI centre. An adopted plan can still be appealed.

    Verda AI centre, Sundsvall (Almåsen) →Source: Sundsvalls kommun (Sundsvall växer)

  3. 7 December 2026

    In 24 days

    Scheduled

    Deadline · Telenor Sverige

    Acceptance period ends for Telenor’s mandatory offer for Bahnhof

    Telenor’s unconditional cash offer of SEK 62 per share runs from 9 November to 7 December 2026 at 17:00 CET. Bahnhof operates five halls in the register.

    Bahnhof Pionen →Bahnhof Thule →Bahnhof Gullan →Bahnhof S:t Erik →Bahnhof Sparven →Source: Telenor Sverige AB

  4. 14 December 2026

    Scheduled

    Milestone · Telenor Sverige

    Expected settlement of Telenor’s offer for Bahnhof

    Telenor gives 14 December 2026 as the expected settlement date for shares tendered in the mandatory offer.

    Bahnhof Pionen →Bahnhof Thule →Bahnhof Gullan →Bahnhof S:t Erik →Bahnhof Sparven →Source: Telenor Sverige AB

  5. Q4 2026

    Scheduled

    Planning · Enköping municipality

    Detailed-plan work for Ullunda expected to start

    The municipality started a development project for a data centre at Ullunda on 30 September 2026. A planning decision is to be sought, and detailed-plan work is expected to start in the fourth quarter of 2026 if it is granted.

    Planned data centre, Enköping (Ullunda) →Source: Enköpings kommun

2027

  1. Early 2027

    Company target

    Commissioning · EcoDataCenter

    First data center at EcoDataCenter Borlänge due

    When construction started on 24 September 2025 the operator said the first data center on the Kvarnsveden campus was scheduled for completion in early 2027.

    EcoDataCenter Borlänge →Source: EcoDataCenter

  2. 30 April 2027

    Scheduled

    Deadline · Kistinge Infrastruktur (Therma Loop)

    Last day for Therma Loop to say whether it buys the Kistinge land

    Under the letter of intent backed by Halmstad’s community-development committee on 22 September 2026, the company must say before 30 April 2027 whether it wants to buy the land. Otherwise the letter lapses.

    Therma Loop data centre, Halmstad (Kistinge) →Source: Halmstads kommun

  3. Q2 2027

    Company target

    Construction start · Fossefall

    Construction start expected for Fossefall’s AI factory in Jokkmokk

    Fossefall signed a 65 MW grid connection agreement with Vattenfall Eldistribution on 10 November 2026 and expects construction to start in the second quarter of 2027. No final investment decision has been taken.

    Fossefall AI factory, Jokkmokk →Source: Fossefall

  4. Q4 2027

    Company target

    Commissioning · atNorth

    atNorth SWE02 in Akalla scheduled to go live

    atNorth announced the 30 MW metro site on 29 January 2026 and gave the fourth quarter of 2027 as its target for going live.

    atNorth SWE02 Akalla →Source: atNorth

  5. 2027

    Company target

    Milestone · atNorth and Calentix

    Heat purchase agreement targeted for SWE04 and Långsele district heating

    Calentix’s project page gives 2027 as the target for a heat purchase agreement, with 1.6 MW in a first phase and potential for about 20 MW.

    atNorth SWE04 Sollefteå →Source: Calentix Energy

  6. 2027

    Company target

    Commissioning · EcoDataCenter and Mistral AI

    Scheduled opening of the Mistral AI data center in Borlänge

    EcoDataCenter said on 11 February 2026 that it will design, build and operate an AI-focused data center at its Borlänge site, with Mistral deploying compute and an opening scheduled for 2027.

    EcoDataCenter Borlänge →Source: EcoDataCenter

  7. 2027

    Company target

    Construction start · EcoDataCenter

    Construction start expected for EcoDataCenter in Smedjebacken

    EcoDataCenter signed an option on 52 hectares at Röbacken in August 2026. It says construction starts once the building permit and environmental permit are granted, which it expects during 2027.

    EcoDataCenter Smedjebacken (Röbacken) →Source: EcoDataCenter

2028

  1. First half of 2028

    Company target

    Commissioning · atNorth

    atNorth SWE04 in Sollefteå expected operational

    On 23 February 2026 atNorth confirmed plans for a 300 MW data center at Hamre Industrial Park and said it expects operations in the first half of 2028.

    atNorth SWE04 Sollefteå →Source: atNorth

  2. Autumn 2028

    Company target

    Grid · E.ON and atNorth

    200 MW grid connection for SWE04 planned to be in operation

    Sollefteå municipality reported on 28 May 2026 that E.ON and atNorth had signed a 200 MW connection agreement for Långsele, with operation planned for autumn 2028.

    atNorth SWE04 Sollefteå →Source: Sollefteå kommun

  3. 2028

    Company target

    Commissioning · Google

    Target completion for Google’s data center in Horndal

    Google broke ground in June 2026. Its location page gives 2028 as the target completion date and notes that the timeline can change.

    Google Horndal →Source: Google Data Centers

2029

  1. March 2029

    Company target

    Grid · E.ON Energidistribution and Enersense

    Two 130 kV lines between Hamre and Nässe due to be completed

    Enersense said on 3 November 2026 that E.ON had contracted it to build two overhead lines of about 2.5 kilometres each, linked to atNorth’s campus. Work starts in November 2026 and is due to be completed in March 2029.

    atNorth SWE04 Sollefteå →Source: Enersense International Plc

  2. Q2 2029

    Company target

    Milestone · atNorth and Calentix

    First heat delivery from SWE04 to Långsele district heating

    Calentix gives the second quarter of 2029 as the target for first delivery of recovered heat from the data center to the Långsele network.

    atNorth SWE04 Sollefteå →Source: Calentix Energy

  3. 2029

    Company target

    Commissioning · EcoDataCenter

    First data center at EcoDataCenter Smedjebacken expected in operation

    The operator's release of 25 August 2026 gives 2029 for the first data center in operation on the Röbacken campus.

    EcoDataCenter Smedjebacken (Röbacken) →Source: EcoDataCenter

2033

  1. Around 2033

    Company target

    Commissioning · Panattoni and E.ON

    Preliminary target for opening Panattoni’s data centre at Hässleholm Nord

    Hässleholm municipality gives around 2033 as the preliminary target for opening, the same year as E.ON’s first connection indication of 150 MW. The letter of intent is not binding.

    Panattoni data centre, Hässleholm Nord →Source: Hässleholms kommun