Published 2026-09-12 · Event 2026-06-30
Fingrid’s Kristinestad–Nokia page is 2026 general design, not reserved west-coast hall power

Fingrid’s Kristinestad–Nokia project page writes field work from late 2024 through summer 2026 and general design finishing in 2026, with construction 2026–2029. A design year is not reserved offtake.
Fingrid’s Kristinestad–Nokia project page is the dated design source used here. It writes a new 400+110 kV connection of about 180 kilometres between new substations at Åback in Kristinestad and at Nokia. The municipalities listed are Kristinestad, Karijoki, Isojoki, Kankaanpää, Karvia, Parkano, Ikaalinen, Ylöjärvi, Hämeenkyrö and Nokia. Between Kristinestad and Isojoki the page writes two parallel 400+110 kV connections. A 180-kilometre design page is not reserved hall offtake.
The process sentence must stay a process sentence. Route stretches for further design were chosen in August 2024. The statutory EIA programme is written as October 2022, the EIA report as July 2023, a supplement in spring 2024 and the coordinating authority’s reasoned conclusion in June 2024. Those are EIA facts. They are not a construction decision on every stretch and not a reserved megawatt.
The timetable sentence must stay a timetable sentence. Field work for general design is written as starting in late 2024 and ending in summer 2026, with general design finishing in 2026. Construction is written as 2026–2029 depending on the stretch. General design is split into Åback–Honkajoki and Honkajoki–Nokia, with TLT-Building Oy named for that work. A 2026 design finish is not a live west-coast hall.
Related grid notes stay on their own pages. Fingrid’s Seinäjoki–Hirvisuo EIA-report note, the Harjulinja programme opinion, the Lakeuslinja Natura note and other Ostrobothnia rows are different dates and different instruments. This article does not import a reserved hall offtake into a 2026 general-design year.
DataCenterSweden records summer 2026 as a Fingrid general-design and field-work window for Kristinestad–Nokia. No project identifier is attached. The next update would need a later primary source that names general design as finished, a stretch under construction, or a reserved consumption agreement beside the 180 kilometres. Until then, the 2026 design year stays a grid paper — not reserved west-coast hall capacity.
Why it matters
A 180-kilometre 400+110 kV headline on Finland’s west coast is easy to file as spare hall power. The page is usable only if the 2026 design year stays a design year — not a reservation.
What remains unknown
The page does not finish the 2026 general design, put every stretch under construction or name a reserved hall offtake beside Kristinestad–Nokia.
Sources
- Kristinestad–Nokia 400+110 kV — Fingrid project page — Fingrid (publication date not stated). Checked 2026-09-12.