Published 2026-09-12 · Event 2026-09-01

Vattenfall’s Lextorp–Lunden page is an autumn-2026 construction start, not reserved Trollhättan hall power

An industrial interior with equipment carts and overhead pipework.
Photo Lawrence Krowdeed on Unsplash

Vattenfall Eldistribution’s Lextorp–Lunden page writes two new 40 kV lines from Lextorp to a planned Lunden station, with construction starting in autumn or winter 2026. A start window is not reserved offtake.

Vattenfall Eldistribution’s Lextorp–Lunden project page is the dated start-window source used here. It writes two new 40 kV lines between the existing Lextorp station and a planned Lunden station in Trollhättan Municipality. Trollhättan Energi is written as planning the new Lunden transformer station, south-east of Trollhättan, because the town is expanding eastwards. Two 40 kV ties to a municipal station are not reserved hall offtake.

The permit sentence must stay a permit sentence. A consult is written as having been held in spring 2023. Concession is written as received in September 2024. Those are permission rows. They are not a construction start and not a reserved megawatt.

The timetable sentence must stay a timetable sentence. Construction start is written as autumn or winter 2026, and the work is written as planned ready in the first quarter of 2027. A first-quarter 2027 finish is not a live Trollhättan hall.

Related grid notes stay on their own pages. Vattenfall’s other Västra Götaland regional-grid rows are different dates and different voltages. This article does not import a named tenant or a reserved hall offtake into an autumn-or-winter 2026 start window.

DataCenterSweden records autumn or winter 2026 as a Vattenfall construction-start window for Lextorp–Lunden. No project identifier is attached. The next update would need a later primary source that names the two 40 kV lines as under construction or in service, or a reserved consumption agreement with a printed megawatt. Until then, the 2026 start stays a municipal-station tie — not reserved Trollhättan hall capacity.

Why it matters

A Trollhättan east-expansion headline is easy to file as spare hall power. The page is usable only if the autumn-or-winter start stays a 40 kV municipal tie — not a reservation.

What remains unknown

The page does not start the autumn-or-winter 2026 works, finish Q1 2027 or give a reserved hall megawatt beside Lextorp–Lunden.

Sources

  1. Lextorp–Lunden two 40 kV lines — concession and 2026 start Vattenfall Eldistribution (publication date not stated). Checked 2026-09-12.