Published 2026-09-12 · Event 2026-09-01
Vattenfall’s Lextorp–Lunden page is an autumn-2026 construction start, not reserved Trollhättan hall power

Vattenfall Eldistribution’s Lextorp–Lunden page writes two new 40 kV lines from Lextorp to a planned Lunden station, with construction starting in autumn or winter 2026. A start window is not reserved offtake.
Vattenfall Eldistribution’s Lextorp–Lunden project page is the dated start-window source used here. It writes two new 40 kV lines between the existing Lextorp station and a planned Lunden station in Trollhättan Municipality. Trollhättan Energi is written as planning the new Lunden transformer station, south-east of Trollhättan, because the town is expanding eastwards. Two 40 kV ties to a municipal station are not reserved hall offtake.
The permit sentence must stay a permit sentence. A consult is written as having been held in spring 2023. Concession is written as received in September 2024. Those are permission rows. They are not a construction start and not a reserved megawatt.
The timetable sentence must stay a timetable sentence. Construction start is written as autumn or winter 2026, and the work is written as planned ready in the first quarter of 2027. A first-quarter 2027 finish is not a live Trollhättan hall.
Related grid notes stay on their own pages. Vattenfall’s other Västra Götaland regional-grid rows are different dates and different voltages. This article does not import a named tenant or a reserved hall offtake into an autumn-or-winter 2026 start window.
DataCenterSweden records autumn or winter 2026 as a Vattenfall construction-start window for Lextorp–Lunden. No project identifier is attached. The next update would need a later primary source that names the two 40 kV lines as under construction or in service, or a reserved consumption agreement with a printed megawatt. Until then, the 2026 start stays a municipal-station tie — not reserved Trollhättan hall capacity.
Why it matters
A Trollhättan east-expansion headline is easy to file as spare hall power. The page is usable only if the autumn-or-winter start stays a 40 kV municipal tie — not a reservation.
What remains unknown
The page does not start the autumn-or-winter 2026 works, finish Q1 2027 or give a reserved hall megawatt beside Lextorp–Lunden.
Sources
- Lextorp–Lunden two 40 kV lines — concession and 2026 start — Vattenfall Eldistribution (publication date not stated). Checked 2026-09-12.