Jämtland County · SE2

Strömsund

Strömsund has one data-centre file in the register: the Norwegian developer Arcem AS wants to investigate a data centre on Hoting 8:1 and 8:6 in Hoting, about 57,000 square metres of municipal land. On 10 November 2026 the executive committee's working committee proposed that the executive committee approve a land allocation agreement. No power capacity is stated.

A land allocation agreement (markanvisningsavtal) reserves municipal land for a developer while it investigates a project; it is not a sale. According to the minutes, Arcem will investigate ground conditions, the power that can be delivered, the detailed plan and regulatory requirements. An overhead line along an existing power line from the nearest substation, 725 metres away, is described as very important for the placement.

The company's employment figures in the minutes are examples: a facility of about 10 MW would employ 100 to 300 people during the most intensive construction period and 20 to 30 permanently. The capacity has not been set.

Arcem data centre, Strömsund (Hoting) — ProposedBahnhof Bunker, Gothenburg — Under constructionStendörren data centre, Södertälje (Almnäs) — In developmentData centre, Hylte (Hyltebruk, Västra Åkralt) — In developmentPanattoni data centre, Hässleholm Nord — ProposedGoogle Torsboda, Timrå — AnnouncedEcoDataCenter Smedjebacken (Röbacken) — In developmentFossefall AI factory, Jokkmokk — In developmentEcoDataCenter Norrsundet (Gävle) — ProposedData centre, Ockelbo (Vallhalla, Lingbo) — In developmentTherma Loop data centre, Halmstad (Kistinge) — ProposedSunSpark data centre, Gotland (Visby) — ProposedMagnora data centre, Tranemo (Limmared) — ProposedSunSpark data centre, Torsås (Söderåkra) — ProposedPlanned data centre, Enköping (Ullunda) — ProposedMagnora data centre, Hultsfred (Nyhagen) — ProposedRoofscapes data centre, Bräcke — AnnouncedVerda AI centre, Sundsvall (Almåsen) — AnnouncedEdgeConneX Skellefteå — In developmentMeta Luleå — OperationalGoogle Horndal — Under constructionMicrosoft Gävle — OperationalMicrosoft Sandviken — OperationalMicrosoft Staffanstorp — OperationalEcoDataCenter Falun — Partially operationalEcoDataCenter Borlänge — Under constructionatNorth SWE01 Kista — OperationalatNorth SWE02 Akalla — In developmentatNorth SWE04 Sollefteå — In developmentEquinix SK1 — OperationalEquinix SK2 — OperationalEquinix SK3 — OperationalConapto Stockholm 3 North — OperationalDigital Realty Stockholm — OperationalSTACK STO01 Stockholm — OperationalBahnhof Pionen — OperationalBahnhof Thule — OperationalBahnhof Gullan — OperationalBahnhof S:t Erik — OperationalBahnhof Sparven — OperationalConapto Stockholm South — OperationalGleSYS Falkenberg — OperationalGleSYS Stockholm — Operationalevroc Arlandastad — Under constructionHydro66 Svenska, Boden — Operational

Documented projects in the register

Questions for a concrete establishment

  • Does the executive committee approve the land allocation agreement, and for how long does it run?
  • Which network owner serves the site, and how much power can it deliver?
  • Will Arcem buy the land, and at what price?

Actors here

Arcem

About electricity area SE2 →