Falkenberg · Halland County · SE4
GleSYS Falkenberg
GleSYS west-coast data center. The current operator page states 5 MW total capacity, PUE 1.2, 100% renewable energy and district-heat recovery. A 1 October 2020 release said heat delivery to Falkenberg Energi had started and listed 3 MW utility power at completion.
Fact box
- Actor
- GleSYS
- Last checked
- 2026-09-10
- Location accuracy
- municipality · Approximate location
Approximate Falkenberg location. 2020 release named Kanslistvägen 12.
Phases
- Falkenberg hall — Operational
Capacity disclosure
Announced capacity (definition unclear)
5 MW
ReportedAs of 2026-09-10 · GleSYS
“With a total capacity of 5 MW”
Utility power
3 MW
ReportedAs of 2020-10-01 · GleSYS / Mynewsdesk
Historical utility-power figure from the 2020 heat-recovery release. Shown as a dated claim, not silently replaced by 5 MW.
“Utility Power: 3 MW”
Planning and grid
Operating hall completed around 2020 according to the heat-recovery release.
Operator now states 5 MW total capacity. The 2020 release stated 3 MW utility power. The difference is unresolved in public wording.
Updates
2020-10-01
GleSYS says heat delivery to Falkenberg Energi has started
A 1 October 2020 GleSYS release said surplus energy from the new Falkenberg hall had begun supplying district heat. That documents a start of delivery, not a later measured annual volume.
Knowledge gaps
- Whether 5 MW superseded 3 MW through expansion is not explained on the cited pages.
- Measured annual heat delivery after 2020 is not in those pages.
Sources
- GleSYS Falkenberg data center — GleSYS, 2026-01-01. Checked 2026-09-10.
- Surplus energy from a new data center is transformed into district heating — GleSYS / Mynewsdesk, 2020-10-01. Checked 2026-09-10.