Falkenberg · Halland County · SE4
GleSYS Falkenberg
GleSYS west-coast data center. The current operator page states 5 MW total capacity, PUE 1.2, 100% renewable energy and district-heat recovery. A 1 October 2020 release said heat delivery to Falkenberg Energi had started and listed 3 MW utility power at completion.
Fact box
- Actor
- GleSYS
- Status
- Operational
- Municipality / county
- Falkenberg · Halland County
- Bidding zone
- SE4
- Announced capacity (definition unclear)
- 5 MW · GleSYS
- Last checked
- 2026-10-20
- Location accuracy
- Municipality level
Phases
- Falkenberg hall — Operational
Capacity disclosure
Announced capacity (definition unclear)
5 MW
Announced capacity (definition unclear) · current · 2026 · announced · campus
ReportedAs of 2026-09-10 · GleSYS
“With a total capacity of 5 MW”
Utility power
3 MW
Utility power · historic · 2020 · announced · campus
ReportedAs of 2020-10-01 · GleSYS / Mynewsdesk
Historical utility-power figure from the 2020 heat-recovery release. Shown as a dated claim, not silently replaced by 5 MW.
“Utility Power: 3 MW”
Planning and grid
Operating hall completed around 2020 according to the heat-recovery release.
Operator now states 5 MW total capacity. The 2020 release stated 3 MW utility power. The difference is unresolved in public wording.
Updates
2020-10-01
GleSYS says heat delivery to Falkenberg Energi has started
A 1 October 2020 GleSYS release said surplus energy from the new Falkenberg hall had begun supplying district heat. That documents a start of delivery, not a later measured annual volume.
Context
- County: Halland County
- Municipality: Falkenberg
- Electricity area: SE4
- Actors: GleSYS
Related news
- 2026-09-12 · GleSYS’s 1 October 2020 Falkenberg start is dated heat delivery; 26 GWh stays potential
- 2026-09-12 · Heat-recovery readiness is not delivered heat: Horndal, Hamina and the Swedish file
- 2026-09-10 · SE1–SE4 review reading guide: what 29 May 2026 did and did not change
- 2026-09-10 · Stockholm heat reuse: Data Parks invitation versus delivered heat
- 2026-09-10 · West-coast hall and heat: GleSYS Falkenberg’s 3 MW and 5 MW rows
- 2026-09-10 · Grid-queue literacy: indicative, applied, reserved, allocated, energized
Knowledge gaps
- The operator page, read 20 October 2026, states “a total capacity of 5 MW” in its text but shows a “10 MW” counter elsewhere on the same page; the 5 MW row is kept until GleSYS clarifies.
- Whether 5 MW superseded 3 MW through expansion is not explained on the cited pages.
- Measured annual heat delivery after 2020 is not in those pages.
Sources
- GleSYS Falkenberg data center — GleSYS (publication date not stated). Checked 2026-10-20.
- Surplus energy from a new data center is transformed into district heating — GleSYS / Mynewsdesk, 2020-10-01. Checked 2026-09-10.