EcoDataCenter Falun

EcoDataCenter main campus in Falun. The 2025 annual report says buildings C and D were completed and commissioned and that site capacity increased from 29 MW to 41 MW. Buildings E and F were under construction, with a stated 65 MW once they are operational. Marketing pages state 80 MW available power.

Partially operationalGrid: A company press item describes securing 80 MW future power supply with Falu Energi & Vatten and Ellevio. That is operator-reported and is not filed here as a reviewed grid agreement.

Fact box

Last checked
2026-09-10
Location accuracy
district · Approximate location

Approximate Falun location. Operator publishes Slaggvarpsvägen 21 on the site page.

Phases

  • Buildings C and DOperational
  • Buildings E and FUnder construction

Capacity disclosure

  • Announced capacity (definition unclear)

    41 MW

    ReportedAs of 2025-12-31 · EcoDC Holding AB

    Operator annual-report figure after commissioning C and D. IT versus facility definition is not stated in the extracted wording.

    total capacity at the Falun site had increased from 29 MW to 41 MW

  • Announced capacity (definition unclear)

    65 MW

    ReportedAs of 2026-12-31 · EcoDC Holding AB

    Forward-looking campus total if E and F enter operation. Not added on top of the 41 MW figure.

    Once Data Centers E and F are operational, the total capacity in Falun will amount to 65 MW

  • Site power

    80 MW

    ReportedAs of 2026-09-10 · EcoDataCenter

    Operator site-page envelope. A related press item describes securing 80 MW future power supply. Not treated as commissioned IT load.

    Total available power 80MW

Planning and grid

Campus is operating and expanding. Individual detailed-plan files were not reviewed for this launch set.

A company press item describes securing 80 MW future power supply with Falu Energi & Vatten and Ellevio. That is operator-reported and is not filed here as a reviewed grid agreement.

Updates

  • 2025-12-31

    EcoDataCenter reports Falun C and D commissioned; site capacity 41 MW

    The 2025 annual report says data centers C and D were fully completed and commissioned and that Falun site capacity increased from 29 MW to 41 MW. E and F construction began in 2025.

Knowledge gaps

  • IT versus facility definition for 41 / 65 / 80 MW is not fully specified.
  • E and F commissioning dates in the report are targets, not completion certificates.
  • Heat delivered versus heat-recovery design is not quantified here.

Sources

  1. EcoDC Holding AB annual report 2025 (English) EcoDC Holding AB, 2026-04-01. Checked 2026-09-10.
  2. EcoDataCenter 1, Falun EcoDataCenter, 2026-01-01. Checked 2026-09-10.
  3. EcoDataCenter in Falun secures a future power supply of 80 MW EcoDataCenter, 2020-01-01. Checked 2026-09-10.