NewsPublished 2026-11-20 · Event 2026-11-10 · The editorial team
Norwegian developer seeks data-centre land in Hoting, Strömsund; no power figure
A committee in Strömsund municipality in Jämtland proposes a land allocation agreement with Arcem AS for about 57,000 square metres in Hoting, where the Norwegian company wants to investigate a data centre. How much power the site can get is not stated.
The municipal executive committee's working committee in Strömsund proposed on 10 November 2026 that the executive committee approve a land allocation agreement with the Norwegian company Arcem AS. The agreement covers the municipal properties Hoting 8:1 and Hoting 8:6 in Hoting, an area of about 57,000 square metres. The company wants to investigate building and operating a data centre there. The minutes were approved and posted on 17 November. The executive committee meets on 24 November, and according to Östersunds-Posten the case is taken up then.
Hoting has not been in the register as a data-centre site before. Arcem asked to buy the land on 31 August 2026. A land allocation agreement is not a sale. It reserves the land while the company investigates ground conditions, the power that can be delivered, the detailed plan and regulatory requirements. The terms of the agreement, such as how long it runs and whether there is a fee, are not in the minutes.
No power capacity is given. The company's text in the minutes uses two sizes as examples. A facility of about 10 MW would employ 100 to 300 people during the most intensive construction period, and 20 to 30 permanently, plus an estimated 20 to 45 indirect local jobs. A 100 MW project would need 1,000 to 1,500 people during construction and give 50 to 100 permanent jobs. The company writes that it bases its estimates on the lower end until the capacity is set. Construction usually takes 18 to 24 months, in stages.
According to the minutes, the possibility of an overhead line along an existing power line from the nearest substation, 725 metres away, is of great importance for the placement. Which network owner serves the site, and how much capacity is available, is not stated. The register already records that Enersense is to rebuild about 12.6 kilometres of an existing 130 kV line between Hoting and Flybäcken under a contract with E.ON Energidistribution. The minutes do not mention that line.
In proportion, 57,000 square metres is 5.7 hectares. That is less than the about 12.6 hectares Bräcke municipality bought in December 2025 to enable Vostroblock's data-centre development, but more than the about 35,000 square metres in Limmared that Tranemo municipality is preparing for a land deal with Magnora. In the same minutes, the working committee handles a proposed sale of 5,000 square metres of Hoting 8:1 to another company at SEK 20 per square metre. No price is stated for Arcem.
Arcem AS is based in Oslo. According to the minutes, the company has data-centre platforms in Norway, Finland and Sweden. Its website shows projects at Husnes in Kvinnherad, in Elverum and at Bredsand in Moss, all in Norway. Which Swedish platform is meant is not stated.
The register now has an entry for Arcem's data centre in Hoting and a page for Strömsund municipality. The capacity is recorded as not disclosed.
Why it matters
It is a second municipality in Jämtland with a documented data-centre land case, after Bräcke. If the executive committee approves the agreement, the municipality reserves the land for Arcem while the company finds out whether power can be delivered. That question decides whether the site goes further, and it is still open.
Background
Hoting is a village in Strömsund municipality in northern Jämtland, in electricity area SE2. The register's other Jämtland file is Roofscapes' data-centre development in Bräcke, where the council sold land in October 2026. Östersunds-Posten reported the Hoting plans on 19 November.
Questions that remain
- How much power can the site get? The company is to investigate the available power, and the minutes name neither a network owner nor a capacity.
- What does the land allocation agreement say? The minutes refer to the agreement as a basis for the decision but do not give its duration, fee or terms for a later purchase.
- Which Swedish platform does Arcem have? The minutes say the company has platforms in Sweden, but its website shows only Norwegian projects.
- What will the land cost? Another company is offered SEK 20 per square metre for part of Hoting 8:1 in the same minutes, but no price is stated for Arcem.
- How large will the facility be? The employment figures are based on examples of 10 and 100 MW, and the company writes that the capacity has not been set.
What remains unknown
The power capacity, network owner, the terms and duration of the land allocation agreement, any land price, the investment, customers and the timetable are not published.
Sources
- Strömsund Municipality — minutes of the municipal executive committee's working committee, 10 November 2026 (§§ 189–214; § 207 land allocation agreement for industrial use, Hoting 8:1 and 8:6, TSF.2026.1150) — Strömsunds kommun, 2026-11-17. Checked 2026-11-20.
- Strömsund Municipality notice board — working committee minutes 10 November 2026, §§ 189–214 (posted 17 November – 8 December 2026) — Strömsunds kommun, 2026-11-18. Checked 2026-11-20.
- Östersunds-Posten: “Nya planer på datacenter i länet” (19 November 2026) — Östersunds-Posten, 2026-11-19. Checked 2026-11-20.
- Arcem AS — company website (data-centre developer, Oslo) — Arcem AS (publication date not stated). Checked 2026-11-20.
- Enersense press release: Enersense signs two power line contracts in Sweden, including one supporting data centre development (3 November 2026) — Enersense International Plc, 2026-11-03. Checked 2026-11-04.