Smedjebacken · Dalarna County · SE3

EcoDataCenter Smedjebacken

EcoDataCenter announced a planned third Dalarna campus at Röbacken on 25 August 2026. On 8 September the municipal executive board recommended an option-and-lease transaction to the council. The council calendar lists a 21 September meeting, but no minutes from it were available in the published protocol index reviewed on 22 September, so its outcome is unverified here. A 2025 municipal minute records 150 MW could be made available for delivery in 2028–2030; this gives context for the operator’s English 150 MW statement but is not a current site connection contract or defined IT-load metric.

AnnouncedGrid: The English operator notice says 150 MW has an immediate green light, but does not define its boundary. A 2025 Smedjebacken municipal minute records a positive power-availability message from Svenska kraftnät and Vattenfall for 150 MW, with delivery possible in 2028–2030. The sources used here do not establish a final site connection contract, reserved capacity in force today, or energisation date.

Fact box

Last checked
2026-09-22
Location accuracy
municipality · Approximate location

Röbacken industrial area in Smedjebacken Municipality; no parcel-level project coordinate is published in the cited notices.

Phases

  • Röbacken campus proposalAnnounced

Capacity disclosure

  • Announced capacity (definition unclear)

    Conflicting figures

    Announced capacity (definition unclear) · unclear / unclassified · 2026 · announced · campus

    Unclear / conflictingAs of 2026-08-25 · EcoDataCenter

    The English notice contains this wording; the Swedish notice does not define a capacity figure. A 2025 municipal minute independently reports 150 MW as power that could be made available for delivery in 2028–2030. Neither source set defines the figure as IT load, facility load or a current site connection entitlement, so it remains an unclear capacity observation.

    green light of an immediate 150MW

Planning and grid

The 8 September 2026 municipal executive-board minute recommends an option to acquire land via a municipal company and a 6.5-hectare lease. The council calendar lists a 21 September meeting, but no resulting minute was available in the published protocol index reviewed on 22 September. The Swedish operator notice says building and environmental permits were expected during 2027. No final land transfer or permit is recorded here.

The English operator notice says 150 MW has an immediate green light, but does not define its boundary. A 2025 Smedjebacken municipal minute records a positive power-availability message from Svenska kraftnät and Vattenfall for 150 MW, with delivery possible in 2028–2030. The sources used here do not establish a final site connection contract, reserved capacity in force today, or energisation date.

Updates

  • 2026-09-08

    Smedjebacken executive board recommends a land transaction

    The executive board recommended that the municipal council approve an option to acquire Röbacken industrial land through a newly formed municipal company and a lease of 6.5 hectares. This is a recommendation, not a completed sale or final council approval.

  • 2026-08-25

    EcoDataCenter reports plans for a third Dalarna campus

    Paired Swedish and English notices describe 52 hectares at Röbacken but differ on the land instrument. The English-only 150 MW phrase now has historical context in a 2025 municipal record, though its live metric boundary remains undefined.

Knowledge gaps

  • The outcome of the 21 September 2026 council meeting has not been verified in the published minutes available on 22 September; final signed land instruments have not been reviewed.
  • No council approval, building permit, environmental permit or construction start is recorded here.
  • The 150 MW figure has 2025 municipal context for possible power delivery in 2028–2030, but no current site-connection document or IT/facility metric boundary is recorded.
  • No site-level grid agreement, energisation milestone or delivered heat figure is cited.

Sources

  1. EcoDataCenter establishes itself in Smedjebacken Municipality EcoDataCenter, 2026-08-25. Checked 2026-09-22.
  2. EcoDataCenter to establish third datacenter campus in Sweden EcoDataCenter, 2026-08-25. Checked 2026-09-22.
  3. Municipal executive board minutes, 8 September 2026, § 109 Smedjebacken Municipality, 2026-09-08. Checked 2026-09-22.
  4. Municipal council meeting schedule and protocols Smedjebacken Municipality (publication date not stated). Checked 2026-09-23.
  5. Published municipal council minutes Smedjebacken Municipality (publication date not stated). Checked 2026-09-23.
  6. Municipal executive board minutes, 8 April 2025, § 64 Smedjebacken Municipality, 2025-04-08. Checked 2026-09-22.

Submit a documented update · Report an error