Stockholm · Stockholm County · SE3
atNorth SWE01 Kista
Operational atNorth metro site in Kista. The operator page states 6,400 sqm facility size, 12 MW site power capacity, design PUE 1.2, liquid cooling and heat recovery with Stockholm Exergi.
Fact box
- Actor
- atNorth
- Last checked
- 2026-09-10
- Location accuracy
- district · Approximate location
Approximate Kista district location.
Phases
- SWE01 — Operational
Capacity disclosure
Site power
12 MW
ReportedAs of 2026-09-10 · atNorth
“12 MW Site power capacity”
Planning and grid
Operating colocation hall. Permit file not reviewed in this launch set.
Site power capacity is operator-stated at 12 MW. The underlying grid agreement is not published here.
Updates
2026-09-02
atNorth says CPP Investments and Equinix completed an acquisition
atNorth announced that CPP Investments and Equinix completed an acquisition and that atNorth would continue under its existing brand. This is an ownership event, not a capacity or construction change.
Knowledge gaps
- Occupied IT load is not published.
- Heat actually delivered versus recovery design is not quantified on the cited page.
Sources
- SWE01 Stockholm metro site — atNorth, 2026-01-01. Checked 2026-09-10.
- Sweden data centers — atNorth, 2026-01-01. Checked 2026-09-10.
- CPP Investments and Equinix complete atNorth acquisition — atNorth, 2026-09-02. Checked 2026-09-10.