Halmstad · Halland County

Therma Loop data centre, Halmstad (Kistinge)

Proposed data centre on the municipal property Fyllinge 20:432, 13,531 square metres, in the Kistinge industrial area in Halmstad, Halland County. On 22 September 2026 the municipal executive committee's community-development committee backed a letter of intent with Kistinge Infrastruktur AB, a subsidiary of Therma Loop AB (case KS 2026/00451). The letter requires at least 10 MW of connected power. Waste heat is to go to the district-heating network of Halmstads Energi och Miljö AB (HEM).

ProposedGrid: The officer's report says the energy companies must be able to deliver at least 10 MW of connected power to the data centre. No grid company, connection agreement or connection date is named. A HEM presentation mentions a first phase of 10 MW for a "small data centre Fyllinge", possible to double when more power is available.

Fact box

Actor
Status
Proposed
Municipality / county
Halmstad · Halland County
Utility power
10 MW · Halmstads kommun
Last checked
2026-10-30
Location accuracy
Municipality level
Halmstad100 km
Pin placed at Halmstad (OpenStreetMap). The property is Fyllinge 20:432 in the Kistinge industrial area; its exact boundary is shown only on maps in the committee papers.

Phases

    Capacity disclosure

    • Utility power

      10 MW

      Utility power · announced / planned · 2026 · announced · campus

      ReportedAs of 2026-10-30 · Halmstads kommun

      A minimum requirement in the letter of intent, not a connection agreement or IT load.

      “minst 10 megawatt ansluten effekt”

    Planning and grid

    The property has a detailed plan for industrial use. Letter of intent backed by the community-development committee on 22 September 2026 (case KS 2026/00451); it is conditional on a decision that gains legal force. The company is to say before 30 April 2027 whether it wants to buy the land; otherwise the letter lapses. The next step would be a reservation agreement.

    The officer's report says the energy companies must be able to deliver at least 10 MW of connected power to the data centre. No grid company, connection agreement or connection date is named. A HEM presentation mentions a first phase of 10 MW for a "small data centre Fyllinge", possible to double when more power is available.

    Updates

    • 2026-09-22

      Halmstad committee backs letter of intent on a data centre at Kistinge

      The municipal executive committee's community-development committee unanimously backed a letter of intent with Kistinge Infrastruktur AB, a subsidiary of Therma Loop AB, on Fyllinge 20:432 (case KS 2026/00451). The data centre needs at least 10 MW of connected power; the company has until 30 April 2027 to say whether it wants to buy the land.

    Context

    More projects in Halland County

    Related news

    Knowledge gaps

    • No grid company, connection agreement or connection date is given.
    • Investment, timetable and land price are not disclosed.
    • The item number in the committee's minutes of 22 September 2026 has not been checked.
    • Whether the company goes ahead before 30 April 2027 is not known.