Jokkmokk · Norrbotten County · SE1

Fossefall AI factory, Jokkmokk

Planned AI factory (data centre with GPU compute) by Fossefall in Jokkmokk municipality, Norrbotten County. The site covers 350,000 square metres, is planned for industrial use and lies in bidding area SE1. On 10 November 2026 Fossefall said it had signed a grid connection agreement with Vattenfall Eldistribution AB securing 65 MW, with the potential for a further 135 MW (200 MW in total). Construction is expected to start in Q2 2027; no final investment decision has been taken.

In developmentGrid: Grid connection agreement with Vattenfall Eldistribution AB signed according to Fossefall (announced 10 November 2026): 65 MW secured, potential for a further 135 MW. Vattenfall Eldistribution is to carry out the grid works; Fossefall invests in the connection. Connection date not stated.

Show on the map →

Fact box

Status
In development
Municipality / county
Jokkmokk · Norrbotten County
Bidding zone
SE1
Utility power
65 MW · Fossefall
Last checked
2026-11-10
Location accuracy
Municipality level
EdgeConneX Skellefteå — In developmentMeta Luleå — OperationalHydro66 Svenska, Boden — OperationalJokkmokk100 km
Pin placed at the town of Jokkmokk (OpenStreetMap) as a municipality-level marker. Fossefall and the municipality do not name the property or the exact location in the sources used.

Phases

    Capacity disclosure

    • Utility power

      65 MW

      Utility power · current · 2026 · contracted · campus

      DocumentedAs of 2026-11-10 · Fossefall

      Grid capacity in the connection agreement according to Fossefall; not IT load. A further 135 MW is a stated potential only.

      “The agreement secures 65 MW of grid capacity for the project”

    • Announced capacity (definition unclear)

      200 MW

      Announced capacity (definition unclear) · announced / planned · 2026 · announced · campus

      ReportedAs of 2026-11-10 · Fossefall

      Planned total if the further 135 MW is realised. Not contracted.

      “with the potential for an additional 135 MW, bringing the total capacity to 200 MW”

    Planning and grid

    Fossefall says the area is planned for industrial use. Jokkmokk Municipality wrote in May 2026 that it has handled the detailed-plan process for the area over several years and that the plan was financed by the developer. The plan itself, its legal-force date and any environmental permitting have not been checked.

    Grid connection agreement with Vattenfall Eldistribution AB signed according to Fossefall (announced 10 November 2026): 65 MW secured, potential for a further 135 MW. Vattenfall Eldistribution is to carry out the grid works; Fossefall invests in the connection. Connection date not stated.

    Upcoming decisions and dates

    • Q2 2027 · Company target

      Construction start expected for Fossefall’s AI factory in Jokkmokk

      Fossefall signed a 65 MW grid connection agreement with Vattenfall Eldistribution on 10 November 2026 and expects construction to start in the second quarter of 2027. No final investment decision has been taken.

      Source: Fossefall

    The full decision calendar →

    Updates

    • 2026-11-10

      Fossefall signs grid connection agreement with Vattenfall Eldistribution for 65 MW in Jokkmokk

      Fossefall said it has signed a grid connection agreement with Vattenfall Eldistribution AB securing 65 MW for a planned AI factory in Jokkmokk, with the potential for a further 135 MW (200 MW in total). Construction is expected to start in Q2 2027; no final investment decision has been taken.

    Context

    More projects in Norrbotten County

    Related news

    Knowledge gaps

    • The property, exact location and detailed plan are not named in the sources used.
    • When the 65 MW becomes available and on what terms the further 135 MW could be added are not stated.
    • No final investment decision has been taken; the investment amount is not published.
    • Vattenfall Eldistribution has not published its own notice in the sources checked.