atNorth
Nordic colocation operator with an operational Stockholm site and further Swedish sites in development.
Operator pages list SWE01 in Kista as operational with 12 MW site power. A 29 January 2026 notice and the SWE02 page announce a 30 MW metro site in Akalla, scheduled to go live in Q4 2027. A 23 February 2026 notice announces plans to develop a 300 MW mega site at Hamre, Sollefteå, expected operational in H1 2028. Those later figures are announced or planned site power, not live IT load.
On 2 September 2026 atNorth said CPP Investments and Equinix completed an acquisition. atNorth said it would continue to operate under its existing brand.
A profile is not a quality stamp.
Related projects
Related news
- 2026-09-12 · Stockholm’s Akalla page is a heat-and-lease site file, not Barings’ 30 MW
- 2026-09-12 · atNorth’s 6 September 2023 SWE01 paper is a heat-recovery cooling design, not a 2026 megawatt-hour
- 2026-09-12 · atNorth’s 2 September 2026 notice names four Nordic mega sites; a name is not a live megawatt
- 2026-09-12 · Sollefteå council approves the Hamre agreement proposal; a vote is not a groundbreaking
- 2026-09-12 · Heat-recovery readiness is not delivered heat: Horndal, Hamina and the Swedish file
- 2026-09-12 · Sollefteå reports an E.ON 200 MW connection agreement for atNorth in Långsele
Sources
- Sweden data centers — atNorth, 2026-01-01. Checked 2026-09-10.
- SWE01 Stockholm metro site — atNorth, 2026-01-01. Checked 2026-09-10.
- SWE02 Stockholm metro site — atNorth, 2026-01-29. Checked 2026-09-11.
- New 30MW metro data center in Stockholm, Sweden — atNorth, 2026-01-29. Checked 2026-09-11.
- New 300MW mega site in Sollefteå, Sweden — atNorth, 2026-02-23. Checked 2026-09-11.
- CPP Investments and Equinix complete atNorth acquisition — atNorth, 2026-09-02. Checked 2026-09-10.