NewsPublished 2026-11-16 · Event 2026-11-10 · The editorial team

Temporary permit for site huts and storage on the Vallhalla data-centre property in Ockelbo

Västra Gästriklands samhällsbyggnadsförvaltning granted a temporary permit on 10 November 2026 for a construction-site establishment with site huts, parking and storage on Vallhalla 1:125 west of Lingbo. A building permit for a data centre on the same property was granted on 16 October. The notice does not name the applicant.

Stendörren data centre, Södertälje (Almnäs) — In developmentGoogle Torsboda, Timrå — AnnouncedEcoDataCenter Smedjebacken (Röbacken) — In developmentEcoDataCenter Norrsundet (Gävle) — ProposedPlanned data centre, Enköping (Ullunda) — ProposedRoofscapes data centre, Bräcke — AnnouncedVerda AI centre, Sundsvall (Almåsen) — AnnouncedGoogle Horndal — Under constructionMicrosoft Gävle — OperationalMicrosoft Sandviken — OperationalEcoDataCenter Falun — Partially operationalEcoDataCenter Borlänge — Under constructionatNorth SWE01 Kista — OperationalatNorth SWE02 Akalla — In developmentEquinix SK1 — OperationalEquinix SK2 — OperationalEquinix SK3 — OperationalConapto Stockholm 3 North — OperationalDigital Realty Stockholm — OperationalSTACK STO01 Stockholm — OperationalBahnhof Pionen — OperationalBahnhof Thule — OperationalBahnhof Gullan — OperationalBahnhof S:t Erik — OperationalConapto Stockholm South — OperationalGleSYS Stockholm — Operationalevroc Arlandastad — Under constructionOckelbo100 km
Data centre, Ockelbo (Vallhalla, Lingbo). The position is approximate.

According to a notice on Ockelbo municipality's notice board, Västra Gästriklands samhällsbyggnadsförvaltning has granted a temporary permit for a new construction-site establishment with site huts, parking and storage on the property Vallhalla 1:125 in Ockelbo municipality. The decision is dated 10 November 2026 and has case number VGS-BYGG 2026-000570. The notice was posted the same day.

Vallhalla 1:125 is the property where the administration granted a building permit on 16 October 2026 for a data centre with offices, guardhouse, water treatment plant, sprinkler facility, garage, switchgear, transformer station, wall and parking (VGS-BYGG 2026-000365). A permit for a transformer station on the same property followed on 23 October (VGS-BYGG 2026-000522).

The new notice does not name the applicant and does not say what the site establishment is for, how long the temporary permit applies or when work is to begin. The plan documents for the Vallhalla industrial area state that a plan agreement was signed with Hyperco Oy, Sverige filial.

A temporary permit for a site establishment is not a start notice for the data centre. No start notice for the data-centre buildings has been published. The municipality states that decisions on the notice board gain legal force when they have been published for 28 days; for the data-centre permit posted on 19 October that period ends on 16 November, provided the decision is not appealed. DataCenterSweden has not seen any confirmation that the permit has gained legal force.

The register entry for the Vallhalla data centre now lists the temporary permit among the project's permits.

Why it matters

The permit covers a construction-site establishment, with site huts, parking and storage, on the property where the data centre has a building permit. It is the first permit decision on the property published since the data-centre permits in October.

Questions that remain

  • Who is behind the build? None of the three notices names the applicant. The plan documents mention a plan agreement with Hyperco Oy, but no source says that company applied for the permits.
  • How large will the data centre be? The building permit lists a switchyard and a transformer station, but no power figure is published.
  • Is the power there? No network owner has disclosed a connection agreement or a connection date for the property.
  • Has the data-centre permit been appealed? The appeal period ended on 16 November, and nobody has confirmed that the permit is in legal force.
  • Why a temporary permit already? A site establishment before a start notice suggests that someone expects construction to begin, but the notice does not say when.

What remains unknown

The applicant, the duration of the temporary permit, whether the data-centre permit has been appealed, when a start notice is issued, the power capacity and the connection date are not published.

How the project has developed

  1. 2026-11-10Temporary permit for a construction-site establishment on Vallhalla 1:125 in Ockelbo
  2. 2026-10-16Building permit granted for a data centre on Vallhalla 1:125 in Ockelbo