NewsPublished 2026-11-23 · Event 2026-11-20 · The editorial team

Ellevio rebuilds the Borlänge grid for the Kvarnsveden data centre; work runs to 2032

The grid company Ellevio is rebuilding the Kvarnsveden switchgear in Borlänge for the data centre being established on the industrial area, and reinforcing the lines from the Repbäcken station. The project is due to be complete in 2032, when a new transmission line can be connected. How much power the data centre gets, and when, is not stated.

Stendörren data centre, Södertälje (Almnäs) — In developmentGoogle Torsboda, Timrå — AnnouncedEcoDataCenter Smedjebacken (Röbacken) — In developmentEcoDataCenter Norrsundet (Gävle) — ProposedData centre, Ockelbo (Vallhalla, Lingbo) — In developmentPlanned data centre, Enköping (Ullunda) — ProposedVerda AI centre, Sundsvall (Almåsen) — AnnouncedGoogle Horndal — Under constructionMicrosoft Gävle — OperationalMicrosoft Sandviken — OperationalEcoDataCenter Falun — Partially operationalatNorth SWE01 Kista — OperationalatNorth SWE02 Akalla — In developmentEquinix SK1 — OperationalEquinix SK2 — OperationalEquinix SK3 — OperationalConapto Stockholm 3 North — OperationalDigital Realty Stockholm — OperationalSTACK STO01 Stockholm — OperationalBahnhof Pionen — OperationalBahnhof Thule — OperationalBahnhof Gullan — OperationalBahnhof S:t Erik — OperationalConapto Stockholm South — OperationalGleSYS Stockholm — Operationalevroc Arlandastad — Under constructionBorlänge100 km
EcoDataCenter Borlänge. The position is approximate.

Ellevio has put up a project page on reinforcing the regional grid in Borlänge and connecting a data centre. According to the page, Ellevio is rebuilding the Kvarnsveden switchgear on the industrial area itself "for the new data centre being established there". The data centre is not named. On the former paper mill at Kvarnsveden, EcoDataCenter is building its second campus, which is the EcoDataCenter Borlänge entry in the register. Ellevio's sitemap gives 20 November 2026 as the page's last change.

What is new is that the network owner itself now describes work for the data centre. Until now the register had no grid information for Borlänge: neither EcoDataCenter's annual report nor the February 2026 partnership notice with Mistral AI named a connection. At the construction start in September 2025, EcoDataCenter said the campus would have access to 250 MW at launch. Ellevio's page gives no power figure.

The project mainly concerns the Repbäcken regional substation north-west of Borlänge and the regional line through the northern part of town. The regional grid is the level between Svenska kraftnät's transmission grid and the local networks. Repbäcken has reached the end of its technical life. A new part of the switchgear is being built next to the existing one, which is then demolished, and the rebuild runs from autumn 2026 to summer 2029. The line from Repbäcken is reinforced and partly put underground, and the number of lines goes from two to four. East of the river, where the cable becomes an overhead line, part of the work also reinforces the grid towards Falun to give redundancy. The other lines run to the Kvarnsveden station, where they will supply the data centre.

The whole project starts in 2026 and is expected to be complete in 2032. That is the year Ellevio expects Svenska kraftnät's new transmission line to the area to be ready for connection to the new station. Ellevio's capacity page for Dalarna, updated on 16 October 2026, names it as a further 400 kV line between Bäsna and Repbäcken, around 2032. Svenska kraftnät's project page gives a concession decision in 2028, construction start in 2029/2030 and planned commissioning in 2031/2032. Svenska kraftnät writes that the line is needed to meet its connection obligation towards the regional network owner.

The two Ellevio pages give different years. The capacity page gives 2030 for new 145 kV lines from Repbäcken to Kvarnsveden and 2028–2030 for the renewal and reinforcement of the Repbäcken station. The project page gives autumn 2026 to summer 2029 for the station rebuild. The pages do not say whether this is the same work.

The data centre's timetable is ahead of the grid. EcoDataCenter has said the first data centre at Kvarnsveden is to be ready in early 2027, and the Mistral AI data centre on the site has a scheduled opening in 2027. According to Ellevio, the new lines to Kvarnsveden come in 2030 and the transmission line around 2032. None of the sources says how the first halls are supplied until then. Ellevio writes that there will be noise and heavy traffic during the works, with some impact on roads for limited periods.

Why it matters

It is the first time the network owner has described the connection of the Kvarnsveden data centre. The page shows that full grid capacity to the area depends on Svenska kraftnät's Bäsna–Repbäcken line, where a concession decision is expected in 2028. That makes the transmission-grid timetable part of the campus timetable, even though the data centre itself is due to open earlier.

Background

The land at the former Kvarnsveden paper mill is described as acquired by EcoDataCenter in 2024. The company announced construction start on 24 September 2025. On 29 January 2026 Borlänge's environment and planning board gave a positive plan notice for part of Kvarnsveden 3:392 (plan 673). In February 2026 EcoDataCenter and Mistral AI announced a partnership for an AI-focused data centre on the same site. EcoDataCenter also operates a campus in Falun and plans a third in Smedjebacken.

The power figure in context

250 MW ranks number 4 among the 20 projects in the register that publish a figure. The figures are of different kinds and must not be added together.

Published power by project, MW
EdgeConneX Skellefteå1,000 MW
Panattoni data centre, Hässleholm Nord300 MW
atNorth SWE04 Sollefteå300 MW
EcoDataCenter Borlänge250 MW
EcoDataCenter Smedjebacken (Röbacken)150 MW
Fossefall AI factory, Jokkmokk65 MW
Data centre, Hylte (Hyltebruk, Västra Åkralt)60 MW

Questions that remain

  • How much power will Ellevio deliver to Kvarnsveden? The project page gives no MW, and EcoDataCenter's 250 MW is the company's statement of access at launch, not a disclosed grid agreement.
  • How are the first halls supplied in 2027? According to Ellevio the new lines to Kvarnsveden come in 2030 and the transmission line around 2032, and no source describes an arrangement for the time before that.
  • When is the rebuild of the Kvarnsveden switchgear finished? The project page gives dates for Repbäcken but not for the switchgear on the industrial area.
  • Is the 2028–2030 renewal of Repbäcken on the capacity page the same work as the autumn 2026 to summer 2029 rebuild on the project page? Ellevio does not explain the difference.
  • What happens to the timetable if the Bäsna–Repbäcken concession is delayed? Svenska kraftnät expects a decision in 2028, and Ellevio ties the end of the project to that line.

What remains unknown

How much power Ellevio will deliver to Kvarnsveden, whether a connection agreement has been signed, when the rebuild of the Kvarnsveden switchgear is finished, what the work costs and who pays for it are not stated.

How the project has developed

  1. 2026-11-20Ellevio describes the grid work for the data centre at Kvarnsveden in Borlänge
  2. 2026-02-11EcoDataCenter and Mistral AI announce a Borlänge partnership
  3. 2025-09-24EcoDataCenter starts construction at Kvarnsveden, Borlänge

Every event and source in the register

Sources

  1. Ellevio — “Förstärkning av Borlänges regionnät och anslutning av datacenter” (project page, Dalarna) — Ellevio (publication date not stated). Checked 2026-11-23.
  2. Ellevio — grid capacity in the Dalarna regional network area (updated 16 October 2026) — Ellevio, 2026-10-16. Checked 2026-11-23.
  3. Bäsna–Repbäcken — project hub (concession filing) — Svenska kraftnät, 2026-06-08. Checked 2026-09-12.
  4. EcoDataCenter breaks ground on mega campus in Borlänge — EcoDataCenter, 2025-09-24. Checked 2026-10-20.
  5. Mistral AI and EcoDataCenter Partner to Build AI-focused Data Center in Sweden — EcoDataCenter, 2026-02-11. Checked 2026-09-11.