Fossefall plans an AI factory (data centre with GPU compute) on a 350,000-square-metre site in Jokkmokk planned for industrial use, in bidding area SE1. On 10 November 2026 the company said it had signed a grid connection agreement with Vattenfall Eldistribution AB securing 65 MW, with the potential for a further 135 MW. Construction is expected to start in Q2 2027 if a final investment decision is taken.

In May 2026 Fossefall described the platform as planned for up to 200 MW, with an initial phase of about 45 MW. Jokkmokk Municipality said on 12 May 2026 that it welcomed the plan, that it has handled the detailed-plan process for the area over several years and that the plan was financed by the developer.

The connection agreement announced on 10 November 2026 is the first published grid agreement for the project. Under it Vattenfall Eldistribution carries out the grid works and Fossefall invests in the connection. The property and connection date are not named.

Data centre, Hylte (Hyltebruk, Västra Åkralt) — In developmentPanattoni data centre, Hässleholm Nord — ProposedGoogle Torsboda, Timrå — AnnouncedEcoDataCenter Smedjebacken (Röbacken) — In developmentFossefall AI factory, Jokkmokk — In developmentEcoDataCenter Norrsundet (Gävle) — ProposedData centre, Ockelbo (Vallhalla, Lingbo) — In developmentTherma Loop data centre, Halmstad (Kistinge) — ProposedSunSpark data centre, Gotland (Visby) — ProposedMagnora data centre, Tranemo (Limmared) — ProposedSunSpark data centre, Torsås (Söderåkra) — ProposedPlanned data centre, Enköping (Ullunda) — ProposedMagnora data centre, Hultsfred (Nyhagen) — ProposedRoofscapes data centre, Bräcke — AnnouncedVerda AI centre, Sundsvall (Almåsen) — AnnouncedEdgeConneX Skellefteå — In developmentMeta Luleå — OperationalGoogle Horndal — Under constructionMicrosoft Gävle — OperationalMicrosoft Sandviken — OperationalMicrosoft Staffanstorp — OperationalEcoDataCenter Falun — Partially operationalEcoDataCenter Borlänge — Under constructionatNorth SWE01 Kista — OperationalatNorth SWE02 Akalla — In developmentatNorth SWE04 Sollefteå — In developmentEquinix SK1 — OperationalEquinix SK2 — OperationalEquinix SK3 — OperationalConapto Stockholm 3 North — OperationalDigital Realty Stockholm — OperationalSTACK STO01 Stockholm — OperationalBahnhof Pionen — OperationalBahnhof Thule — OperationalBahnhof Gullan — OperationalBahnhof S:t Erik — OperationalBahnhof Sparven — OperationalConapto Stockholm South — OperationalGleSYS Falkenberg — OperationalGleSYS Stockholm — Operationalevroc Arlandastad — Under constructionHydro66 Svenska, Boden — Operational

Documented projects in the register

Questions for a concrete establishment

  • Which detailed plan covers the site, and when did it gain legal force?
  • When does the 65 MW become available, and on what terms could the further 135 MW be added?
  • When does Fossefall take the final investment decision?