Skåne County · SE4

Hässleholm

Hässleholm's municipal executive committee approved a letter of intent with the property developer Panattoni on 10 June 2026 to investigate a hyperscale data centre of about 300 MW at Hässleholm Nord. E.ON has given a first positive connection indication of 150 MW for around 2033.

The letter of intent is not legally binding and either party can end it. It reserves about 20 hectares, roughly a fifth of the land that will be available to companies when Hässleholm Nord is fully built out.

According to the municipality, 300 MW is about five to six times the present power level of Hässleholm town. E.ON's grid study is expected to take 6 to 18 months, followed by a preliminary study of 3 to 9 months. The municipality is changing the detailed plan for a new main entrance from Stobyvägen.

Panattoni says the cooling technology needs no water, and that it is in dialogue with Hässleholm Miljö AB on whether surplus heat can be used in the district heating network. Nothing is decided on heat.

Data centre, Hylte (Hyltebruk, Västra Åkralt) — In developmentPanattoni data centre, Hässleholm Nord — ProposedGoogle Torsboda, Timrå — AnnouncedEcoDataCenter Smedjebacken (Röbacken) — In developmentFossefall AI factory, Jokkmokk — In developmentEcoDataCenter Norrsundet (Gävle) — ProposedData centre, Ockelbo (Vallhalla, Lingbo) — In developmentTherma Loop data centre, Halmstad (Kistinge) — ProposedSunSpark data centre, Gotland (Visby) — ProposedMagnora data centre, Tranemo (Limmared) — ProposedSunSpark data centre, Torsås (Söderåkra) — ProposedPlanned data centre, Enköping (Ullunda) — ProposedMagnora data centre, Hultsfred (Nyhagen) — ProposedRoofscapes data centre, Bräcke — AnnouncedVerda AI centre, Sundsvall (Almåsen) — AnnouncedEdgeConneX Skellefteå — In developmentMeta Luleå — OperationalGoogle Horndal — Under constructionMicrosoft Gävle — OperationalMicrosoft Sandviken — OperationalMicrosoft Staffanstorp — OperationalEcoDataCenter Falun — Partially operationalEcoDataCenter Borlänge — Under constructionatNorth SWE01 Kista — OperationalatNorth SWE02 Akalla — In developmentatNorth SWE04 Sollefteå — In developmentEquinix SK1 — OperationalEquinix SK2 — OperationalEquinix SK3 — OperationalConapto Stockholm 3 North — OperationalDigital Realty Stockholm — OperationalSTACK STO01 Stockholm — OperationalBahnhof Pionen — OperationalBahnhof Thule — OperationalBahnhof Gullan — OperationalBahnhof S:t Erik — OperationalBahnhof Sparven — OperationalConapto Stockholm South — OperationalGleSYS Falkenberg — OperationalGleSYS Stockholm — Operationalevroc Arlandastad — Under constructionHydro66 Svenska, Boden — Operational

Documented projects in the register

Questions for a concrete establishment

  • What does E.ON's grid study say about the second 150 MW?
  • When is the changed detailed plan for the new entrance adopted?
  • Who will operate the data centre that Panattoni develops?