Skåne County · SE4
Hässleholm
Hässleholm's municipal executive committee approved a letter of intent with the property developer Panattoni on 10 June 2026 to investigate a hyperscale data centre of about 300 MW at Hässleholm Nord. E.ON has given a first positive connection indication of 150 MW for around 2033.
The letter of intent is not legally binding and either party can end it. It reserves about 20 hectares, roughly a fifth of the land that will be available to companies when Hässleholm Nord is fully built out.
According to the municipality, 300 MW is about five to six times the present power level of Hässleholm town. E.ON's grid study is expected to take 6 to 18 months, followed by a preliminary study of 3 to 9 months. The municipality is changing the detailed plan for a new main entrance from Stobyvägen.
Panattoni says the cooling technology needs no water, and that it is in dialogue with Hässleholm Miljö AB on whether surplus heat can be used in the district heating network. Nothing is decided on heat.
Documented projects in the register
- Panattoni data centre, Hässleholm Nord — Proposed
Questions for a concrete establishment
- What does E.ON's grid study say about the second 150 MW?
- When is the changed detailed plan for the new entrance adopted?
- Who will operate the data centre that Panattoni develops?
Actors here
Sources
- Hässleholm municipality: Major data centre investment may become reality at Hässleholm Nord — Hässleholms kommun, 2026-06-04. Checked 2026-11-11.
- Hässleholm municipality: Questions and answers on the planned data centre establishment (Hässleholm Nord) — Hässleholms kommun, 2026-11-02. Checked 2026-11-11.