NewsPublished 2026-11-18 · Event 2026-11-17 · The editorial team
Bahnhof raises its Gothenburg rock-cavern data centre to 20 MW; opening slips to late 2027
Bahnhof says it has decided to raise the capacity of Bahnhof Bunker, its data centre under Bunkerberget in central Gothenburg, to 20 MW because of demand. Commissioning moves from the first quarter of 2027 to the end of 2027. Who supplies the power is not stated.
Bahnhof said in its interim report for the third quarter of 2026, published on 17 November, that it has decided to double the capacity of Bahnhof Bunker in Gothenburg to 20 MW because of growing demand for secure services in rock caverns. As a direct effect, commissioning is now planned for the end of 2027. The data centre is being built in a cavern of about 6,000 square metres, 30 metres under Bunkerberget in central Gothenburg, which was blasted out as a shelter during the Second World War and later used by SKF as an industrial bunker.
Both the figure and the date are new. On its specification page in January 2026, Bahnhof stated 12 MW of total power capacity. In the interim report of 18 August 2026 the company said commissioning was planned for the first quarter of 2027. When Bahnhof wound down its Elementica project in September 2025 and turned to the Gothenburg cavern, it said the opening would be in 2026. The timetable has thus moved twice in just over a year.
The report is not fully consistent. In one place it gives the end of 2027 as the new commissioning date, and in the chief executive's statement it says the higher power shifts the timetable to the second half of 2027. Bahnhof also calls the change a doubling, but the 12 MW in its own January specification does not double to 20. The August report described eight underground halls, each built for a guaranteed load of 1 MW, with up to 4.5 MW possible in a single hall. The company does not explain which figure the doubling starts from.
The report says the first potential large customers have visited the site. No customer is named. It does not say who supplies the electricity, whether a connection agreement for 20 MW exists, or how much the facility will cost. The 20 MW is the company's planned power, not stated as IT load, the power available to servers.
In proportion, 20 MW is a mid-sized figure. Stendörren said on 17 November that it has an agreement for 20 MW of electrical capacity for its planned data centre at Almnäs in Södertälje, atNorth states 12 MW for SWE01 in Kista, and Conapto stated 24 MW for its Stockholm south campus in 2024. The figures are defined differently and should not be added up. Bunker is the first Bahnhof facility in the register with a published power figure; the register's entries for Pionen, Thule, Gullan, S:t Erik and Sparven have none.
The project also changes owner level. On 17 November Telenor Sverige said it holds about 66.88 percent of the shares and 90.56 percent of the votes in Bahnhof, with its mandatory offer open until 7 December. The register now has an entry for Bahnhof Bunker, which replaces the earlier line in the facility inventory.
Why it matters
A rock-cavern facility with 20 MW would be a large addition for customers who want protected capacity in western Sweden. The delay also means that customers waiting for the facility get it later than the company said in August. Whether 20 MW is realistic depends on a grid connection that the company has not described.
Background
Bahnhof presented the Bunkerberget cavern in May 2025 as its seventh data centre: about 6,000 square metres with nine metres of ceiling height. In September 2025 it wound down its earlier Elementica project to concentrate on the Gothenburg cavern. Bahnhof operates Pionen and several other halls in Stockholm and Sparven in Malmö. Telenor Sverige took control of the company on 6 November 2026.
The power figure in context
20 MW ranks number 12 among the 20 projects in the register that publish a figure. The figures are of different kinds and must not be added together.
| EdgeConneX Skellefteå | 1,000 MW |
|---|---|
| Panattoni data centre, Hässleholm Nord | 300 MW |
| atNorth SWE04 Sollefteå | 300 MW |
| EcoDataCenter Borlänge | 250 MW |
| EcoDataCenter Smedjebacken (Röbacken) | 150 MW |
| Fossefall AI factory, Jokkmokk | 65 MW |
| Bahnhof Bunker, Gothenburg | 20 MW |
Questions that remain
- Who supplies the 20 MW, and is there a connection agreement? The report gives only the company's planned power, not a network owner, agreement or connection date.
- What does the doubling start from? The company's January specification said 12 MW, while the August report described eight halls with 1 MW of guaranteed load each, and neither figure becomes 20 when doubled.
- Is it the end of 2027 or the second half of 2027? The same report gives both, and the timetable has already moved from 2026 and from the first quarter of 2027.
- Who are the potential large customers? Bahnhof says they have visited the site but names none, and demand is the company's reason for the increase.
What remains unknown
Who supplies the power and whether a connection agreement for 20 MW exists, which figure the doubling starts from, whether the new date is the end or the second half of 2027, which customers have visited, and what the facility costs are not known.
How the project has developed
- 2026-11-17Bahnhof raises Bunker to 20 MW and moves commissioning to the end of 2027
- 2026-08-18Bahnhof plans Bunker commissioning for the first quarter of 2027
- 2026-01-21Bahnhof publishes Bunker specification with 12 MW
- 2025-09-24Bahnhof concentrates on Bunker and winds down Elementica
- 2025-05-06Bahnhof announces a data centre in Bunkerberget, Gothenburg
Sources
- Bahnhof interim report Q3 2026 (17 November 2026) — Bahnhof AB (publ) / Cision, 2026-11-17. Checked 2026-11-18.
- Bahnhof interim report Q2 2026 (18 August 2026) — Bahnhof AB (publ) / Cision, 2026-08-18. Checked 2026-11-18.
- A first look inside Bahnhof Bunker — Bahnhof, 2026-01-21. Checked 2026-09-12.
- Bahnhof focuses on Bahnhof Bunker — Elementica is wound down — Bahnhof, 2025-09-24. Checked 2026-09-12.
- Bahnhof press release: “Bahnhof bygger nytt datacenter i Göteborg – intar Bunkerberget” (6 May 2025) — Bahnhof AB (publ) / Cision, 2025-05-06. Checked 2026-11-18.
- Telenor Sverige: second supplement to the offer document for the mandatory cash offer to the remaining shareholders in Bahnhof (17 November 2026) — Telenor Sverige / Cision, 2026-11-17. Checked 2026-11-18.
- Telenor Sverige press release: Completes acquisition of a controlling stake in Bahnhof and launches unconditional mandatory cash offer of SEK 62 per share (6 November 2026) — Telenor Sverige AB, 2026-11-06. Checked 2026-11-06.
- Stendörren Fastigheter press release: “Stendörren säkrar 20 MW elkapacitet för datacenteretablering – ökar potentialen för framtida värdeskapande i Stockholm Syd, Södertälje” (17 November 2026) — Stendörren Fastigheter / Cision, 2026-11-17. Checked 2026-11-17.