NewsPublished 2026-11-17 · Event 2026-11-17 · The editorial team
Stendörren secures 20 MW for its Almnäs data centre in Södertälje; no tenant named
Property company Stendörren Fastigheter says it has signed an agreement for 20 MW of electrical capacity for a planned data centre at Almnäs in Södertälje, with the connection expected in the first half of 2028. Who will use or buy the centre is not stated.
Stendörren Fastigheter said in a press release on 17 November 2026 that it has signed an agreement for 20 megawatts of electrical capacity for its planned data centre in Stockholm Syd, Södertälje. The project covers about 20,000 square metres of gross floor area on the company's property Almnäs 5:23. The company expects the grid connection to be completed in the first half of 2028.
What is new is the agreement. When the company reported the building permit in its interim report on 21 July 2026, its chief executive said only that it saw good prospects of securing an initial 20 megawatts, with the possibility of gradually increasing to 40. The company now writes that the 20 MW is contracted. The 40 MW remains a possibility the company says it has identified, not an agreement.
The release does not say who the agreement is with. It does not name a network owner, and it does not say whether the 20 MW is a connection agreement, a capacity reservation or something else. The figure is electrical capacity. It is not stated as IT load, the power available to servers, which is normally lower.
The company does not describe itself as the future operator. A development manager is quoted that the agreement strengthens the project's commercial attractiveness and the possibilities to realise the property's value through future leasing or sale. No tenant, operator or investment decision is published. Stendörren describes itself as a property company in logistics, warehousing and light industry.
In proportion, 20 MW is a mid-sized figure for the Stockholm region. In the register, atNorth states 12 MW of site power for SWE01 in Kista and 30 MW for SWE02 in Akalla, and Conapto stated 24 MW for its south campus in 2024. Those figures are defined in different ways and should not be compared directly or added up. Further afield, Fossefall signed a 65 MW connection agreement with Vattenfall Eldistribution for Jokkmokk on 10 November, and the applicant for the Hylte data centre states about 60 MW of IT capacity.
The register now has an entry for the Almnäs data centre and a page for Södertälje municipality. The 20 MW is recorded as the company's contracted electrical capacity, with the counterparty unknown.
Why it matters
The company itself calls access to electrical capacity a decisive precondition for data-centre projects. With a building permit and a signed capacity agreement, Almnäs becomes a site that a data-centre operator could take over or lease, rather than a plot with prospects. It is also an example of a property company preparing a data-centre site for sale or lease instead of building for its own use.
Background
Almnäs is an industrial area in Södertälje that Stendörren refers to as Stockholm Syd. In July 2026 the company also signed a 15-year lease with a publicly owned company for a new light-industrial building on the same property, Almnäs 5:23. DataCenterSweden wrote about the data-centre permit in July and then attached no register entry, because there was no agreement on power.
The power figure in context
20 MW ranks number 12 among the 20 projects in the register that publish a figure. The figures are of different kinds and must not be added together.
| EdgeConneX Skellefteå | 1,000 MW |
|---|---|
| Panattoni data centre, Hässleholm Nord | 300 MW |
| atNorth SWE04 Sollefteå | 300 MW |
| EcoDataCenter Borlänge | 250 MW |
| EcoDataCenter Smedjebacken (Röbacken) | 150 MW |
| Fossefall AI factory, Jokkmokk | 65 MW |
| Stendörren data centre, Södertälje (Almnäs) | 20 MW |
Questions that remain
- Who is the agreement with? The release names neither a network owner nor another counterparty, so it is not possible to tell whether it is a connection agreement or a reservation.
- Who will use the data centre? The company talks of future leasing or sale but names no tenant, buyer or operator, so it is not known whether anyone has committed to the site.
- How much IT load does 20 MW give? The company states electrical capacity, not IT capacity, and gives no split between servers, cooling and other load.
- What would 40 MW take? The company says the possibility has been identified but not which grid reinforcements or what timetable it requires.
- Will 2028 hold? The connection is expected in the first half of 2028, but the company does not say when construction of the data centre itself would begin.
What remains unknown
The counterparty to the agreement, the network owner, the type of agreement, the tenant or buyer, the investment, the construction timetable and the municipal permit decision's date and case number are not published.
How the project has developed
- 2026-11-17Stendörren signs agreement for 20 MW of electrical capacity at Almnäs
- 2026-07-21Stendörren reports building permit for a data centre at Almnäs
Sources
- Stendörren Fastigheter press release: “Stendörren säkrar 20 MW elkapacitet för datacenteretablering – ökar potentialen för framtida värdeskapande i Stockholm Syd, Södertälje” (17 November 2026) — Stendörren Fastigheter / Cision, 2026-11-17. Checked 2026-11-17.
- Interim report January–June 2026 — Stendörren Fastigheter AB — Stendörren Fastigheter / Cision, 2026-07-21. Checked 2026-09-12.