NewsPublished 2026-11-26 · Event 2026-11-06 · The editorial team
EcoDataCenter applies for an environmental permit in Smedjebacken; comments by 7 December
EcoDataCenter has applied to the Land and Environment Court for a permit for backup power and a data centre on its land in Smedjebacken, where it plans its third campus in Dalarna. Comments are due by 7 December. The notice does not say how large the backup power will be or which fuel it will use.
In short
- EcoDC Falun AB seeks a permit for backup power units with an associated data centre in Smedjebacken (case M 5797-26).
- It is the first known permit application for the Röbacken campus, which the company says will have 150 MW initially.
- The Seveso Act applies and an environmental impact statement is filed. Power and fuel are not given in the notice.
- Comments are due by 7 December. A building permit and a grid agreement are still missing.

What happened
EcoDataCenter has filed its application for an environmental permit for the campus in Smedjebacken. The Land and Environment Court at Nacka District Court has published the application in a notice dated 6 November (case M 5797-26).
The applicant, EcoDC Falun AB, seeks a permit to build and operate backup power units with an associated data centre on the properties Västansjö 2:7, Norrbärke Prästårds 2:1 and Smedjebacken 2:1. Backup power units supply electricity if the grid fails. An environmental impact statement has been submitted. According to the notice, the Seveso Act also applies, the law on preventing and limiting the consequences of major chemical accidents.
What is new: the first permit step after the land deal
In August EcoDataCenter said it had signed an option on 52 hectares in the Röbacken industrial area and expected construction to start in 2027 once the building permit and environmental permit were in place. The municipal council approved the land deal on 21 September. According to the council papers, the industrial land is part of Västansjö 2:7, the first property named in the application.
The applicant is therefore not a new company for Smedjebacken. According to the 2025 annual report, EcoDC Falun AB runs the data centre operations at the Falun site. The council papers say EcoDataCenter is making the purchase through a subsidiary, without naming it.
EcoDataCenter's power figures in Dalarna
Four company figures for the three sites, in megawatts. Smedjebacken is the highlighted bar.
| Item | MW |
|---|---|
| Falun (capacity at end of 2025) | 41 |
| Falun (once buildings E and F are operational) | 65 |
| Smedjebacken (initial capacity, planned) | 150 |
| Borlänge (access at launch) | 250 |
The figures are of different kinds and must not be added together. None is defined as IT load or connection capacity.
Source: EcoDC Holding AB, 2026-04-01; EcoDataCenter, 2026-11-11; EcoDataCenter, 2025-09-24.
Why a court is examining it
Under the Environmental Assessment Ordinance, the Land and Environment Court examines combustion plants with a total installed rated thermal input of more than 300 megawatts. Plants of 50 to 300 megawatts are examined by the county administrative board. The notice gives no power, fuel, number of units or the provision the application falls under, so it does not show why the case is before the court.
By comparison, Hylte municipality said in November that a dialogue was under way with the Halland county administrative board on the permit to operate Magnora's planned data centre in Hyltebruk, including the backup power.
What happens next
Written comments on the application and the environmental impact statement must reach the court by 7 December. The case may be decided without a main hearing. The documents are available at the court and at the citizens' office in Smedjebacken town hall.
A permit is not enough to build. A building permit is also needed, and no such application is known. In its third-quarter report EcoDataCenter states an initial capacity of 150 MW and a construction start in 2027. No grid agreement is published. Under the land agreement, 45 per cent of the price falls due only when the company has signed a grid agreement for at least 150 MW, no later than 31 December 2032.
Smedjebacken among the register's projects in the county
Published power in the register for the largest projects and the projects in this article. EcoDataCenter Smedjebacken (Röbacken): number 2 of 3.
| Item | MW |
|---|---|
| EcoDataCenter Borlänge (utility power) | 250 |
| EcoDataCenter Smedjebacken (Röbacken) (announced capacity (definition unclear)) | 150 |
| EcoDataCenter Falun (announced capacity (definition unclear)) | 41 |
The figures are of different kinds (site, IT or unclear power) and must not be added together.
Source: the DataCenterSweden register, where every figure has its own source.
Why it matters
The application is the first known formal permit step towards construction at Röbacken, and it covers both the backup power and the data centre. Anyone who wants to comment on the application and the environmental impact statement has until 7 December, after which the case may be decided without a main hearing.
Timeline
- 17 August 2026Option and share transfer agreements for the Röbacken land are dated [2]
- 25 August 2026EcoDataCenter signs option on 52 hectares in Smedjebacken for a third campus [3]
- 21 September 2026Smedjebacken council approves land sale to EcoDataCenter via Röbacken 1 AB [2]
- 6 November 2026EcoDataCenter's application for an environmental permit in Smedjebacken is published by the Land and Environment Court [1]
- 10 November 2026EcoDataCenter states an initial capacity of 150 MW for the Smedjebacken campus [4]
- 7 December 2026Last day for comments to the Land and Environment Court [1]
What we do not know yet
- How large the backup power will be, how many units it covers and which fuel they will use.
- Which hazardous substances make the Seveso Act apply, and in what quantities.
- Which provision of the Environmental Assessment Ordinance the application falls under, and so why the court is the first instance.
- Which company will own and run the campus.
- Which grid operator will connect the campus, and when a grid agreement will be signed.
Questions that remain
- How large is the backup power and which fuel will it use? The notice gives neither, and according to the notice the documents, including the environmental impact statement, are held at the court and the municipality; we have not found them published online.
- Why is the case before the court and not the county administrative board? The combustion threshold is 300 MW rated thermal input, but the notice does not give the activity code the application falls under.
- Will the campus be run by the Falun company? The applicant is EcoDC Falun AB, while the council papers say the purchase is made through a subsidiary that is not named.
- When will the grid agreement come? 45 per cent of the land price depends on an agreement for at least 150 MW, but who will supply the power is not published.
Sources
- Nacka District Court, Land and Environment Court — Public notice, case M 5797-26: EcoDC Falun AB applies for a permit to build and operate backup power units with an associated data centre in Smedjebacken (6 November 2026) — Nacka tingsrätt, mark- och miljödomstolen, 2026-11-06. Checked 2026-11-26.
- Smedjebacken Municipality — municipal council minutes 21 September 2026 (§§ 34–45; § 44 land sale to EcoDataCenter, dnr 2024/00349) — Smedjebackens kommun, 2026-09-21. Checked 2026-11-19.
- EcoDataCenter establishes itself in Smedjebacken municipality (press release, Swedish) — EcoDataCenter, 2026-08-25. Checked 2026-11-11.
- EcoDC Holding AB (publ) — interim report Q3 2026 (Swedish, dated 10 November 2026) — EcoDataCenter, 2026-11-11. Checked 2026-11-19.
- EcoDC Holding AB annual report 2025 (English) — EcoDC Holding AB, 2026-04-01. Checked 2026-09-10.
- Environmental Assessment Ordinance (SFS 2013:251), chapter 21, sections 8–10: permit classes for combustion plants — Sveriges riksdag. Checked 2026-11-26.
- Hylte municipality: “Information om planerat projekt: Datacenter i Hyltebruk” (news item, 12 November 2026) — Hylte kommun, 2026-11-12. Checked 2026-11-13.
- EcoDataCenter breaks ground on mega campus in Borlänge — EcoDataCenter, 2025-09-24. Checked 2026-10-20.