NewsPublished 2026-11-19 · Event 2026-11-10 · The editorial team

EcoDataCenter puts Smedjebacken at 150 MW; last land payment waits for a grid deal

EcoDataCenter states an initial capacity of 150 MW for its planned campus in Smedjebacken. The council minutes show that 45 percent of the land price, about SEK 125 million, is paid only once the company signs a grid agreement for at least 150 MW. Who will supply the power is not stated.

Stendörren data centre, Södertälje (Almnäs) — In developmentEcoDataCenter Norrsundet (Gävle) — ProposedData centre, Ockelbo (Vallhalla, Lingbo) — In developmentPlanned data centre, Enköping (Ullunda) — ProposedGoogle Horndal — Under constructionMicrosoft Gävle — OperationalMicrosoft Sandviken — OperationalEcoDataCenter Falun — Partially operationalEcoDataCenter Borlänge — Under constructionatNorth SWE01 Kista — OperationalatNorth SWE02 Akalla — In developmentEquinix SK1 — OperationalEquinix SK2 — OperationalEquinix SK3 — OperationalConapto Stockholm 3 North — OperationalDigital Realty Stockholm — OperationalSTACK STO01 Stockholm — OperationalBahnhof Pionen — OperationalBahnhof Thule — OperationalBahnhof Gullan — OperationalBahnhof S:t Erik — OperationalConapto Stockholm South — OperationalGleSYS Stockholm — Operationalevroc Arlandastad — Under constructionSmedjebacken100 km
EcoDataCenter Smedjebacken (Röbacken). The position is approximate.

EcoDataCenter writes in its interim report for the third quarter of 2026, dated 10 November, that the 52-hectare campus in Smedjebacken has a planned construction start in 2027, "with an initial capacity of 150 MW and the possibility of further expansion". The trade site Entreprenaden repeated the figure on 18 November. When the company and the municipality presented the deal on 25 August, no power figure was given.

The figure also appears in the papers behind the municipal council's decision of 21 September 2026 (item 44), which approved the option agreement and the share transfer agreement with EcoDataCenter. They state that in early 2024 the company received a positive answer that 150 MW could be made available, with delivery in 2028 to 2030. The minutes do not say who gave that answer. A positive answer is not a grid agreement, and the land deal treats the agreement as a condition that remains to be met. The register had not covered the council decision until now.

The deal is built as a company sale. The municipality forms Röbacken 1 AB, which buys about 51.6 hectares of industrial land from the municipality. EcoDataCenter has the right to buy all shares in the company, and thereby the land, within 18 months of the agreement date. The price is SEK 540 per square metre, about SEK 278 million. Payment comes in three steps: an option fee of 5 percent, about SEK 13.9 million, which the municipality keeps if the option is not exercised; 50 percent on the day of access; and 45 percent when the company enters into a grid agreement for at least 150 MW, but no later than 31 December 2032. That last part is about SEK 125 million and is indexed to the consumer price index from 2028. The company also leases 6.5 hectares for 20 years as a construction area.

The price is high for the place. The ordinary rate for zoned industrial land at Röbacken is SEK 160 per square metre, and the municipality justifies more than three times that with a large continuous area and good access to power. An external valuation gives SEK 1.3 to 1.6 million per MW. The minutes do not say which power the valuation is based on. Counted on 150 MW, the range is SEK 195 to 240 million, below the agreed price. In proportion, 150 MW is more than three and a half times the 41 MW that EcoDataCenter's 2025 annual report gives for the operating campus in Falun, and more than twice the 65 MW expected there once buildings E and F are complete. In Hässleholm, E.ON has given Panattoni a positive connection indication of the same size, 150 MW, for around 2033.

The timetables do not match. The council papers say the company aims to start groundwork in autumn 2026, that work to move a road starts in autumn 2026, and that the first data centre is expected to be ready in 2028 or 2029. The August releases said construction would start once the building permit and environmental permit are granted during 2027, with the first data centre in operation in 2029. The job figures also differ: 125 to 150 permanent jobs in the releases, 150 to 200 according to the company in the council papers, and 250 to 300 construction workers during the build.

The agreements carry conditions. The company has undertaken to apply Swedish collective agreements or equivalent terms during construction and operation, with a penalty for breaches. The municipality pays half of any extra costs caused by existing pollution. The parties are to start a project by 2027 on optimising use of the regional grid. The parent company EcoDC Holding AB stands as guarantor. Representatives of six parties moved to approve the proposal.

Why it matters

The figure makes Smedjebacken the largest stated EcoDataCenter campus in Dalarna, but the land deal shows that the power is not yet contracted. The municipality receives almost half of the price only when a grid agreement exists or at the end of 2032, so both the build and the municipality's income depend on a network owner that no source names.

Background

Smedjebacken and EcoDataCenter signed a letter of intent in 2019 and a new one in 2025. In June 2025 the municipal executive commissioned a detailed plan for the Röbacken industrial area. EcoDataCenter operates a campus in Falun, is building in Borlänge and is consulting on an environmental permit for Norrsundet in Gävle. Smedjebacken would be its third campus in Dalarna.

The power figure in context

150 MW ranks number 5 among the 20 projects in the register that publish a figure. The figures are of different kinds and must not be added together.

Published power by project, MW
EdgeConneX Skellefteå1,000 MW
Panattoni data centre, Hässleholm Nord300 MW
atNorth SWE04 Sollefteå300 MW
EcoDataCenter Borlänge250 MW
EcoDataCenter Smedjebacken (Röbacken)150 MW
Fossefall AI factory, Jokkmokk65 MW
Data centre, Hylte (Hyltebruk, Västra Åkralt)60 MW

Questions that remain

  • Who gave the answer on 150 MW for delivery in 2028 to 2030, and has it become a grid agreement? The minutes name neither a network owner nor the status of an agreement.
  • Is 150 MW IT load or connection capacity? The interim report says "initial capacity" without a definition, and the land-deal condition only says "at least 150 MW".
  • Will groundwork start in autumn 2026 as the council papers said? The company and the municipality have otherwise spoken of construction in 2027 once permits are granted, and no application is known.
  • Which power is the valuation of SEK 1.3 to 1.6 million per MW based on? Counted on 150 MW the agreed price is above the range, and the minutes do not explain the difference.
  • Has EcoDataCenter exercised the option? The deadline is 18 months after the agreement date, and half the price is paid only on access.

What remains unknown

Who gave the positive answer on 150 MW and who will be the network owner, whether 150 MW is IT load or connection capacity, whether the option has been exercised, when the building and environmental permit applications will be filed, and what the campus will cost are not known.

How the project has developed

  1. 2026-11-10EcoDataCenter states an initial capacity of 150 MW for the Smedjebacken campus
  2. 2026-09-21Smedjebacken council approves land sale to EcoDataCenter via Röbacken 1 AB
  3. 2026-08-25EcoDataCenter signs option on 52 hectares in Smedjebacken for a third campus

Every event and source in the register

Sources