· SE2
Västernorrland County
Is a 50-hectare development plot in Sollefteå a commissioned load in Västernorrland? It is not. The county includes Sollefteå municipality, where atNorth on 23 February 2026 confirmed plans to develop a 300 MW SWE04 campus at Hamre Industrial Park. That figure is announced or planned site power. It is not live IT load and is not taken from unofficial directories. The county also includes Sundsvall, where a detailed plan for about 42 hectares at Almåsen, aimed at power-intensive uses such as data centres, was handled by the urban planning committee on 21 October 2026; the municipality announced Verda Cloud Oy's AI centre outside central Sundsvall in February 2026, without a megawatt figure. The county sits in SE2. County-level spare capacity is not published here.
Read Sollefteå first, then the atNorth Sweden pages, then the 2 September 2026 ownership notice, then SE2. The acquisition notice by CPP Investments and Equinix is an ownership event. It does not, in the text used here, restate a SWE04 megawatt figure or convert “under development” into a commissioning certificate. Stockholm metro sites SWE01 and SWE02 belong to Stockholm County; do not pull their operator figures into this county total.
A hectare figure is land. A detailed plan is a municipal instrument described by Boverket. A connection answer is a network-owner paper. Svenska kraftnät enters the file if the load is large enough for transmission-level dialogue, and even then the indicative map is not the application. Most connections are still made to regional or local networks. SE2 is the Sundsvall bidding area; it is not a reserved import at Hamre.
What the sources show is limited on purpose. atNorth names SWE04, a 50-hectare plot, development at Hamre Industrial Park in Långsele, and a 23 February 2026 plan for a 300 MW campus expected operational in H1 2028. That megawatt is announced or planned. Construction status beyond the announcement is not independently verified here. Local heat or environmental investigations are a municipal and environmental-authority question; they are not invented here. The 2026 acquisition notice names Swedish development at Sollefteå without changing the metric.
Common misreads: reading 50 hectares as commissioned IT load; assigning a directory megawatt; treating the Equinix name as if SWE04 were an operating Stockholm IBX; adding SWE01’s 12 MW site-power figure into Västernorrland; treating SE2 as spare northern power; treating site control as a startbesked.
Ask what stage of grid dialogue is public, as opposed to site marketing. Ask which planning documents Sollefteå has published. Ask whether construction status is documented or only land control. Ask whether any first-party megawatt has appeared on atNorth’s Sweden pages after the pages used here. Ask which local heat or environmental investigations exist and who published them.
Keep Stockholm facts out of Långsele. SWE01’s 12 MW site-power sentence, SWE02’s fourth-quarter 2027 target, and Stockholm Exergi heat wording belong to Stockholm County. The 2 September 2026 acquisition notice names Swedish development at Sollefteå without restating a megawatt. Equinix as a new owner name does not turn Hamre into an operating IBX. A hectare is still land. A FAQ “under development” sentence is still not a startbesked.
Ask Sollefteå for the detaljplan that actually covers Hamre Industrial Park, and ask the network owner which paper exists. If both answers are silent, the development file is a site-control and marketing file. That is still a real public hook. It is not a commissioned northern cluster and it is not a Norrbotten campus.
Sundsvall is the second file. The detailed plan for Vattjom 2:42 and Söderåsen 2:6 at Almåsen covers about 42 hectares next to SCA's Töva timber terminal and names data centres as an example of power-intensive use. On 21 October 2026 the urban planning committee handled it ahead of adoption, and, according to its approved minutes, proposed that the council adopt it; the council is expected to decide on 30 November 2026. The plan documents do not name an operator; the municipality announced Verda Cloud Oy's AI centre outside central Sundsvall in February 2026. No megawatt figure has been published, and the municipal executive office notes that cooling-water needs are not investigated.
This county brief proves that Västernorrland, in this register, holds two development files in SE2: an announced 300 MW plan at Hamre in Sollefteå and a detailed plan in progress at Almåsen in Sundsvall without a published megawatt. It does not prove live IT load and does not prove energization.
Documented projects in the register
- Verda AI centre, Sundsvall (Almåsen) — Announced
- atNorth SWE04 Sollefteå — In development
Questions for a concrete establishment
- What stage of grid dialogue is public, as opposed to site marketing?
- Is a hectare figure being read as if it were commissioned IT load?
- Which local heat or environmental investigations exist, and who published them?
- Which Sollefteå planning documents cover Hamre / Långsele?
- Did the 2 September 2026 ownership notice change SWE04 stage or capacity in the text used here?
- Are SWE01 megawatts being kept in Stockholm County, not added into Västernorrland?
- Has Sundsvall's council adopted the Almåsen detailed plan, and has it gained legal force?
Actors here
Verda Cloud Oy · Zoningpartners North AB · atNorth
Related news
- 2026-10-23 · Sundsvall planning committee backs 42-hectare plan for power-intensive industry at Almåsen
- 2026-09-12 · atNorth’s 2 September 2026 notice names four Nordic mega sites; a name is not a live megawatt
- 2026-09-12 · Sollefteå council approves the Hamre agreement proposal; a vote is not a groundbreaking
- 2026-09-12 · Sollefteå reports an E.ON 200 MW connection agreement for atNorth in Långsele
- 2026-09-12 · atNorth confirms plans for a 300 MW Sollefteå campus; H1 2028 is a target, not operation
- 2026-09-12 · Sollefteå says it intends to sign a Hamre development agreement with atNorth
Sources
- Sweden data centers — atNorth, 2026-01-01. Checked 2026-09-10.
- New 300MW mega site in Sollefteå, Sweden — atNorth, 2026-02-23. Checked 2026-09-11.
- Electricity bidding areas — Energimarknadsinspektionen, 2026-01-01. Checked 2026-09-10.
- CPP Investments and Equinix complete atNorth acquisition — atNorth, 2026-09-02. Checked 2026-09-10.
- Detailed development plans — Boverket, 2024-10-17. Checked 2026-09-10.
- Indicative transmission-network capacity map — Svenska kraftnät, 2026-01-01. Checked 2026-09-10.
- Minutes, Sundsvall urban planning committee, 21 October 2026 (§§ 123–140) — Sundsvalls kommun (publication date not stated). Checked 2026-10-26.
- Meeting papers, Sundsvall urban planning committee, 21 October 2026 (officers' report SBN-2025-00470-102) — Sundsvalls kommun (publication date not stated). Checked 2026-10-23.
- Detailed plan for an industrial and business area in Almåsen, Vattjom 2:42 and Söderåsen 2:6 — plan description (adoption version) — Sundsvalls kommun, 2026-10-15. Checked 2026-10-23.
- Urban planning committee says yes to industrial land in Töva — SVT Nyheter Västernorrland, 2026-10-22. Checked 2026-10-23.
- Sundsvall becomes a hub for Europe's next major AI investment — Sundsvalls kommun, 2026-02-05. Checked 2026-10-23.