NewsPublished 2026-11-26 · Event 2026-11-26 · The editorial team

NCC wins SEK 75 million groundworks order for atNorth's Sollefteå data centre

NCC is to carry out the initial ground and infrastructure works for atNorth's SWE04 data centre at Hamre Industrial Park in Långsele. The order is worth about SEK 75 million. It is the first known order for the site itself, but when the works start and what they include is not stated.

In short

  • NCC has been contracted for the initial ground and infrastructure works for SWE04 at Hamre, Långsele.
  • The order is worth about SEK 75 million and is booked in NCC Infrastructure in the fourth quarter of 2026.
  • It is the first published order for the establishment itself. Earlier contracts concerned the grid.
  • Start date, scope and total investment for the campus of up to 300 MW have not been published.
A concrete railway underpass with the words “Välkommen till Långsele”, a road, a pedestrian crossing sign and autumn trees, with overhead railway lines above.
The railway viaduct in Långsele, Sollefteå municipality, October 2015. NCC's groundworks concern Hamre Industrial Park in Långsele; the photo does not show the work site. Resized. Photo Henrik Sendelbach, Wikimedia Commons, CC BY-SA 4.0
Cirenso site, Hamre (Sollefteå) — In developmentArcem data centre, Strömsund (Hoting) — ProposedGoogle Torsboda, Timrå — AnnouncedRoofscapes data centre, Bräcke — AnnouncedVerda AI centre, Sundsvall (Almåsen) — AnnouncedEdgeConneX Skellefteå — In developmentSollefteå100 km
atNorth SWE04 Sollefteå. The position is approximate.

What happened

NCC has been contracted to carry out the initial ground and infrastructure works for atNorth's SWE04 data centre at Hamre Industrial Park in Långsele, about 15 kilometres north-west of Sollefteå. The construction company announced it in a press release on 26 November.

The order value is about SEK 75 million. The order is booked in the NCC Infrastructure business area in the fourth quarter of 2026. According to NCC, the works are to enable atNorth's establishment in the industrial park, where a future campus of up to 300 MW is planned.

What is new: the first order for the site itself

The contracts made public so far concerned the grid. In May Sollefteå municipality said E.ON and atNorth had signed an agreement on a 200 MW connection, and that E.ON plans a new distribution substation at Hamre and a 130 kV line to the Nässe transmission substation. In November Enersense said E.ON had contracted it to build two new 130 kV lines between Hamre and Nässe.

NCC's order is the first published order for works on the data centre establishment itself that we are aware of. The press release does not, however, say when the works start, what they include in detail or who formally is the client.

Sollefteå hydroelectric power plant across the Ångermanälven river in winter.
Sollefteå hydroelectric power plant on the Ångermanälven river, January 2025. The plant is in Sollefteå municipality, about 15 kilometres from Hamre Industrial Park. Resized. Photo Tunegravity, Wikimedia Commons, CC BY-SA 4.0

SEK 75 million in context

For NCC the order is small. The company had revenue of about SEK 56 billion in 2025, and SEK 75 million is roughly 0.13 per cent of that. For the project it is a first item. atNorth has not published a total investment for SWE04, so it is not possible to say what share of the build the groundworks represent.

Enersense's two line contracts with E.ON are worth about EUR 15 million together, but one of them concerns a line in Strömsund. The value of the Hamre–Nässe stretch is not reported, so the figures cannot be compared directly.

SWE04 among the largest projects in the register

Published power in the register for the largest projects and the projects in this article. atNorth SWE04 Sollefteå: number 2 of 21.

SWE04 among the largest projects in the register
ItemMW
EdgeConneX Skellefteå (announced capacity (definition unclear))1,000
atNorth SWE04 Sollefteå (site power)300
Panattoni data centre, Hässleholm Nord (announced capacity (definition unclear))300
EcoDataCenter Borlänge (utility power)250
EcoDataCenter Smedjebacken (Röbacken) (announced capacity (definition unclear))150
Fossefall AI factory, Jokkmokk (utility power)65

The figures are of different kinds (site, IT or unclear power) and must not be added together.

Source: the DataCenterSweden register, where every figure has its own source.

The schedule depends on the grid

atNorth said in February that the campus is to be operational in the first half of 2028. The municipality wrote in May that the facility is planned to be taken into use in autumn 2028. Enersense says the Hamre–Nässe lines are due to be completed in March 2029.

NCC's release gives no operating date. None of the sources says whether the data centre can get power before March 2029, or whether parts of the connection can be energised earlier.

Three dates for the same campus

Months from NCC's order (November 2026) to the dates given by three sources. The longer the bar, the later.

Three dates for the same campus
Itemmonths
atNorth (operational H1 2028 (by June))19
Sollefteå municipality (in use autumn 2028 (from September))22
Enersense (Hamre–Nässe lines complete March 2029)28

Half-years and seasons are converted to the month they end or begin: June 2028 and September 2028. The sources give no exact dates.

Source: atNorth, 2026-02-23; Sollefteå kommun, 2026-05-28; Enersense International Plc, 2026-11-03.

Why it matters

An order for groundworks is the first concrete sign that atNorth is building in Långsele, not just planning. At the same time the dates show that the grid may decide when the data centre can actually go into operation.

Timeline

  1. 23 February 2026atNorth announces a 300 MW SWE04 plan in Sollefteå [2]
  2. 28 May 2026Sollefteå municipality: E.ON and atNorth have signed a 200 MW agreement [3]
  3. 3 November 2026E.ON contracts Enersense for two 130 kV lines Hamre–Nässe, due March 2029 [4]
  4. 4 November 2026atNorth and Calentix sign project development agreement on heat recovery to Långsele [5]
  5. 26 November 2026NCC contracted for the initial ground and infrastructure works at Hamre, order value about SEK 75 million [1]

What we do not know yet

  • When the groundworks start and when they are due to be finished.
  • What the works include: area, roads, underground lines or foundations.
  • Who formally is the client for the works.
  • The total investment for SWE04 and who will build the data halls themselves.
  • Whether the data centre can get power before the Hamre–Nässe lines are complete in March 2029.

Questions that remain

  • When do the works start? The release only says the order is booked in the fourth quarter of 2026, not a start date.
  • Will power arrive in time? atNorth and the municipality speak of operation in 2028, but E.ON's line contractor is due to finish only in March 2029.
  • Who builds the halls? NCC's contract covers initial ground and infrastructure works, and no contractor for the buildings has been made public.
  • How big is the first phase? The release mentions up to 300 MW but says nothing about how much is built first.

Sources

  1. NCC — “NCC utför markarbeten vid nytt datacenter i Sollefteå” (press release, 26 November 2026) — NCC AB (Cision), 2026-11-26. Checked 2026-11-26.
  2. New 300MW mega site in Sollefteå, Sweden — atNorth, 2026-02-23. Checked 2026-09-11.
  3. Municipal report of E.ON’s connection agreement for atNorth in Långsele — Sollefteå kommun, 2026-05-28. Checked 2026-09-12.
  4. Enersense press release: Enersense signs two power line contracts in Sweden, including one supporting data centre development (3 November 2026) — Enersense International Plc, 2026-11-03. Checked 2026-11-04.
  5. Calentix project page: Heat recovery from atNorth's SWE04 data centre to the Långsele district heating network (status November 2026) — Calentix Energy. Checked 2026-11-05.