NewsPublished 2026-11-19 · Event 2026-11-16 · The editorial team

Sundsvall executive backs Almåsen plan; two parties dissent over farmland and water

Sundsvall's municipal executive committee proposed on 16 November that the council adopt the detailed plan for power-intensive industry at Almåsen, where Verda plans an AI centre. A motion to send the case back over farmland, cooling water and wastewater failed. The council decides on 30 November.

Arcem data centre, Strömsund (Hoting) — ProposedGoogle Torsboda, Timrå — AnnouncedEcoDataCenter Norrsundet (Gävle) — ProposedData centre, Ockelbo (Vallhalla, Lingbo) — In developmentRoofscapes data centre, Bräcke — AnnouncedGoogle Horndal — Under constructionMicrosoft Gävle — OperationalMicrosoft Sandviken — OperationalEcoDataCenter Falun — Partially operationalEcoDataCenter Borlänge — Under constructionatNorth SWE04 Sollefteå — In developmentSundsvall100 km
Verda AI centre, Sundsvall (Almåsen). The position is approximate.

Sundsvall's municipal executive committee decided on 16 November 2026 to propose that the municipal council adopt the detailed plan for Vattjom 2:42 et al., an industrial and business area at Almåsen in the Töva area. The full minutes, approved on 18 November and posted on the municipality's notice board on 19 November, show that the decision was not unanimous. Sveriges Radio reported the outcome on 17 November.

What is new compared with the urban planning committee's decision of 21 October is the political line-up. Then the four members from the Moderates and the Sweden Democrats did not take part in the decision. In the executive committee the Moderates supported the proposal, while the Sweden Democrats moved to reject it. The Norrland Party first moved to send the case back for more preparation and, in the alternative, to reject it. The Social Democrats, the Centre Party and the Left Party supported the proposal. The Christian Democrats did not take part in the decision, and one Moderate member declared a conflict of interest. The committee decided to settle the case the same day and then chose the officers' proposal. The Norrland Party and the Sweden Democrats entered reservations.

The motion to send the case back gives the most detailed criticism so far in the case. It cites chapter 3, section 4 of the Environmental Code, under which arable farmland may only be built on if that is needed for an essential public interest and the need cannot be met satisfactorily on other land. It asks the municipality to show the concrete long-term public benefit, how it has itself verified that other locations cannot be used, how traffic, children's safety, noise, cultural environment and feasibility have been weighed, and how water and sewage will be secured in the long run, including cooling-water needs for power-intensive operations, wastewater capacity and who pays if the system must be expanded. The cooling-water question is not new: the municipal executive office noted in its review comment that the need had not been investigated.

The Moderates added a note to the minutes. They write that the area has been designated for industrial land in the comprehensive plan since 2022 and that the party does not oppose adoption, but that the case is overshadowed by the wider question of AI halls and data centres in northern Sweden. The party calls for national responsibility and coordination on power supply, environment and industrial development, and expects future building-permit cases to deal with the questions that have been raised.

The minutes repeat that the plan began on private initiative: Zoningpartners North AB received a positive planning decision in autumn 2025. According to the officers, authorities largely have no remaining objections, while objections mainly from nearby residents could not be met. The council decides because the plan is judged to be of significant public interest. The plan documents name no operator and give no power figure in megawatts; the link to Verda's AI centre comes from the municipality's February 2026 announcement and from SVT. At the same meeting the committee was informed about the sale of Torsboda Industrial Park AB, including parts of a public-benefit agreement, but the minutes record no content.

Why it matters

The plan now goes to the council with a majority behind it, but with a written list of objections that an appeal could build on: farmland under the Environmental Code, alternative sites, and water and cooling. For Verda the plan is a precondition for building permits and environmental permitting, and none of those steps has started in public.

Background

The plan covers about 42 hectares next to SCA's timber terminal in Töva and names data centres as an example of the power-intensive use it is meant for. In February 2026 the municipality announced that the Finnish company Verda Cloud Oy is establishing an AI centre outside central Sundsvall, with Zoningpartners North AB leading preparations. The urban planning committee proposed adoption on 21 October 2026. Local residents have protested against a data centre in the area.

Questions that remain

  • How would cooling water and wastewater for an AI centre be handled? Both the municipal executive office's review comment and the motion to send the case back raise it, and the plan documents do not answer.
  • How much power would an establishment at Almåsen need, and is there a connection agreement? Neither the municipality nor Verda has published a megawatt figure or a connection date.
  • Will the plan be appealed after the council decides? Two parties entered reservations and residents' objections were not met, but nobody has yet said they will appeal.
  • What does the public-benefit agreement for Torsboda contain? The executive committee was informed about parts of it, but the minutes record no content.

What remains unknown

The power capacity, grid connection, investment and timetable for an establishment at Almåsen are not published, nor is how cooling water and wastewater would be handled. Whether the council adopts the plan on 30 November, and whether it is appealed, is not yet known.

How the project has developed

  1. 2026-11-16Sundsvall executive committee proposes adoption of the Almåsen detailed plan
  2. 2026-10-21Sundsvall planning committee proposes adoption of the Almåsen detailed plan
  3. 2026-02-05Sundsvall announces Verda's AI centre

Every event and source in the register

Sources