BEGIN:VEVENT
UID:cal-ockelbo-vallhalla-legal-force-2026-11-16@datacentersweden.se
DTSTAMP:20261113T130944Z
DTSTART;VALUE=DATE:20261116
DTEND;VALUE=DATE:20261117
SUMMARY:Building permit for the Vallhalla data centre can gain legal forc
 e
DESCRIPTION:The permit was granted on 16 October 2026 and posted on 19 Oc
 tober. The municipality states that decisions gain legal force after 28 d
 ays of publication\, which gives 16 November if nobody appeals. No start 
 notice is published.\n\nSource: https://ockelbo.se/kommun--politik/beslut
 --handlingar/anslagstavla/anslagstavla/2026-10-19-bygglov-for-nybyggnad-a
 v-datacenter-kontor-vakthus-vattenreningsverk-med-byggnad-och-tankar-spri
 nkleranlaggning-med-byggnad-och-tankar-garage-stallverk-med-byggnader-tra
 nsformatorstation-och-mur-samt-parkering-har-beviljats-pa-fastighet-vallh
 alla-1125-fallasvagen-51-i-ockelbo-kommun\nhttps://datacentersweden.se/pr
 ojects/ockelbo-vallhalla-lingbo/
URL:https://datacentersweden.se/projects/ockelbo-vallhalla-lingbo/
END:VEVENT
BEGIN:VEVENT
UID:cal-sundsvall-almasen-ks-2026-11-16@datacentersweden.se
DTSTAMP:20261113T130944Z
DTSTART;VALUE=DATE:20261116
DTEND;VALUE=DATE:20261117
SUMMARY:Almåsen detailed plan goes to Sundsvall’s executive committee
DESCRIPTION:The urban planning committee proposed adoption on 21 October 
 2026. According to SVT the plan is handled by the executive committee on 
 16 November before the council decides.\n\nSource: https://www.svt.se/nyh
 eter/lokalt/vasternorrland/stadsbyggnadsnamnden-sager-ja-till-industrimar
 k-i-tova\nhttps://datacentersweden.se/projects/verda-sundsvall-almasen/
URL:https://datacentersweden.se/projects/verda-sundsvall-almasen/
END:VEVENT
BEGIN:VEVENT
UID:cal-sundsvall-almasen-kf-2026-11-30@datacentersweden.se
DTSTAMP:20261113T130944Z
DTSTART;VALUE=DATE:20261130
DTEND;VALUE=DATE:20261201
SUMMARY:Sundsvall council decides on the Almåsen detailed plan
DESCRIPTION:The municipality’s project page gives 30 November 2026 for ad
 option of the plan for the industrial area where Verda plans an AI centre
 . An adopted plan can still be appealed.\n\nSource: https://xn--sundsvall
 vxer-kfb.se/dpalmasen\nhttps://datacentersweden.se/projects/verda-sundsva
 ll-almasen/
URL:https://datacentersweden.se/projects/verda-sundsvall-almasen/
END:VEVENT
BEGIN:VEVENT
UID:cal-telenor-bahnhof-acceptance-2026-12-07@datacentersweden.se
DTSTAMP:20261113T130944Z
DTSTART;VALUE=DATE:20261207
DTEND;VALUE=DATE:20261208
SUMMARY:Acceptance period ends for Telenor’s mandatory offer for Bahnhof
DESCRIPTION:Telenor’s unconditional cash offer of SEK 62 per share runs f
 rom 9 November to 7 December 2026 at 17:00 CET. Bahnhof operates five hal
 ls in the register.\n\nSource: https://news.cision.com/se/telenor-sverige
 /r/telenor-sverige-slutfor-forvarvet-av-en-majoritetspost-i-bahnhof-och-l
 amnar-ett-ovillkorat-kontant-b\,c4420866\nhttps://datacentersweden.se/pro
 jects/bahnhof-pionen/
URL:https://datacentersweden.se/projects/bahnhof-pionen/
END:VEVENT
BEGIN:VEVENT
UID:cal-telenor-bahnhof-settlement-2026-12-14@datacentersweden.se
DTSTAMP:20261113T130944Z
DTSTART;VALUE=DATE:20261214
DTEND;VALUE=DATE:20261215
SUMMARY:Expected settlement of Telenor’s offer for Bahnhof
DESCRIPTION:Telenor gives 14 December 2026 as the expected settlement dat
 e for shares tendered in the mandatory offer.\n\nSource: https://news.cis
 ion.com/se/telenor-sverige/r/telenor-sverige-slutfor-forvarvet-av-en-majo
 ritetspost-i-bahnhof-och-lamnar-ett-ovillkorat-kontant-b\,c4420866\nhttps
 ://datacentersweden.se/projects/bahnhof-pionen/
URL:https://datacentersweden.se/projects/bahnhof-pionen/
END:VEVENT
BEGIN:VEVENT
UID:cal-halmstad-therma-loop-land-deadline-2027-04-30@datacentersweden.se
DTSTAMP:20261113T130944Z
DTSTART;VALUE=DATE:20270430
DTEND;VALUE=DATE:20270501
SUMMARY:Last day for Therma Loop to say whether it buys the Kistinge land
DESCRIPTION:Under the letter of intent backed by Halmstad’s community-dev
 elopment committee on 22 September 2026\, the company must say before 30 
 April 2027 whether it wants to buy the land. Otherwise the letter lapses.
 \n\nSource: https://www.halmstad.se/nyheter/nyhetsarkiv/merverksamhetsmar
 kochnyaforetagsetableringar.22998.html\nhttps://datacentersweden.se/proje
 cts/therma-loop-halmstad-kistinge/
URL:https://datacentersweden.se/projects/therma-loop-halmstad-kistinge/
END:VEVENT