RoundupPublished 2026-11-20 · Event 2026-11-19 · The editorial team
T.Loop plans a data centre in Falköping 230 metres from homes; no decision published
The data-centre company T.Loop plans a data centre on an industrial plot at Nordmannagatan in Falköping, according to Falköpings Tidning and Sveriges Radio. The plot is 230 metres from the nearest homes, and a neighbour calls that far too close. Size, power and grid connection have not been published.

The Swedish company T.Loop, whose legal name is Therma Loop AB, plans a data centre in Falköping in Västra Götaland. According to Falköpings Tidning on 29 October 2026, the plan is to build on a plot at Nordmannagatan, between Besikta and A Lot Decoration. The company's head of development told the paper that if everything goes to plan the data centre will be ready some time in 2028. The paper describes it as a medium-sized regional data centre integrated into the local energy system, with surplus energy going to district heating.
What is new is the local reaction. Sveriges Radio P4 Skaraborg reported on 19 November that the industrial plot is 230 metres from the nearest home, and that a neighbour thinks that is far too close. According to SR, the company's chief executive gave information about why the company wants to build at that particular site.
No size is given in either report. T.Loop's own website says the company typically builds in the range of 10 to 50 MW, and that it often delivers heat to a local district-heating network and support services to the power grid. The two facilities the company runs today are much smaller: STODEC001 in Häggvik, Stockholm, with 0.18 MW since 2023, and STODEC003 at Liljeholmen, Stockholm, with 0.64 MW since 2025. The website says the company has several sites under development in Sweden and the UK, but it does not name Falköping.
The register has one other T.Loop project in Sweden. In Halmstad, a committee of the municipal executive board backed a letter of intent on 22 September 2026 with Kistinge Infrastruktur AB, a T.Loop subsidiary, for the municipal property Fyllinge 20:432 in the Kistinge industrial area. That letter requires at least 10 MW of connected power, and waste heat is to go to the district-heating network of Halmstads Energi och Miljö. The company has until 30 April 2027 to say whether it wants to buy the land.
On noise, the company's website says cooling equipment and backup generators make some sound, that it follows national, regional and municipal noise guidelines, and that it tries to place the noisiest equipment as far as possible from homes and offices. It says the generators run on renewable fuel such as HVO100 and only for a limited number of hours a year: during power cuts, tests and when the grid needs support. These are the company's general statements, not conditions for the Falköping site.
DataCenterSweden has not found a municipal decision, building permit or planning case for the data centre in Falköping municipality's published documents. Without a primary source, the Falköping plans are not entered in the register. The company's website says it takes a final investment decision only when all the pieces, including environmental and building permits, are in place.
Why it matters
It is the second Swedish site outside Stockholm linked to T.Loop in our coverage, after Halmstad, and Falköping has not been in the register before. The distance to homes makes noise and backup power the questions the municipality will have to answer if the company applies for a building permit or a change to the plan.
Background
T.Loop was founded in 2020 and calls its facilities Data Energy Centers: data centres designed to sell their waste heat to district heating and to offer backup power and batteries as grid support. In May 2026 the company said the city of Hanko in Finland had reserved land for one of its facilities. Falköping lies in electricity area SE3.
Questions that remain
- How large will the data centre be? Neither report gives a power figure, and the company's 10–50 MW is a general range, not a figure for Falköping.
- Who owns the plot, and is there a land deal? The reports give the location but not who sells or leases the land.
- Does the detailed plan allow a data centre? The plot is described as industrial land, but no source says whether the plan permits a data centre or needs to change.
- Who takes the heat? The paper mentions district heating, but no agreement with an energy company has been published.
- How will noise be handled 230 metres from homes? The company's guidelines are general, and no noise study for the site has been published.
What remains unknown
The planned power, the land owner and any land deal, whether the plot's detailed plan allows a data centre, the grid owner and connection, the buyer of the heat, the investment and the number of jobs are not published.
Sources
- Sveriges Radio P4 Skaraborg: “Företag vill bygga datacenter 230 meter från villakvarter i Falköping” (19 November 2026) — Sveriges Radio, 2026-11-19. Checked 2026-11-20.
- Falköpings Tidning: “Planerna för datacenter i stan: ’Del av lokala energisystemet’” (29 October 2026) — Falköpings Tidning, 2026-10-29. Checked 2026-11-20.
- T.Loop — Future Sites (company page with questions and answers on sites, heat, noise and backup power) — Therma Loop AB (T.Loop) (publication date not stated). Checked 2026-11-20.
- Halmstad municipality news: More land for businesses and new company establishments (22 September 2026) — Halmstads kommun, 2026-09-22. Checked 2026-10-30.
- Therma Loop expands to Finland and reserves land in Hanko — T.Loop / Mynewsdesk, 2026-05-06. Checked 2026-09-12.