NewsPublished 2026-11-24 · Event 2026-11-23 · The editorial team
Magnora says it holds a permit for 85 MW in southern Sweden, but not where
Magnora Data Center says its Swedish subsidiary has been granted a building permit for an 85 MW data centre in southern Sweden. The company does not name the site. The only known Magnora permit, in Hyltebruk, gives about 60 MW of IT capacity.
Magnora Data Center says its Swedish subsidiary has been granted a building permit for an 85 MW data centre on industrial land in southern Sweden. The statement is in a progress update the Norwegian company published on 23 November. It does not say which municipality granted the permit, where the facility is, or whether the figure is IT capacity or the facility's total power.
The figure cannot be matched to any published decision. The only building permit for a Magnora data centre in Sweden in the DataCenterSweden register is Hylte's. The community-development committee granted a permit for a data centre in Hyltebruk on 21 October, and the municipality has said the permit is held by Magnora Data Center AB with subsidiaries, the same company named in the update. According to the minutes, the applicant states that the building is designed for an installed IT capacity of about 60 MW.
Nor do the company's own earlier figures show 85 MW. Magnora Data Center has described its first Swedish project, in bidding area SE4, as having a planned capacity of 60 MW. In its third-quarter report of 30 October it added two projects in southern Sweden totalling 80 MW. What explains the difference is not stated.
The update also says a project in Säffle in Värmland, in bidding area SE3, has been added. That brings the company's count to four Swedish projects. Magnora appears in municipal papers in Hylte, Tranemo and Hultsfred; the update names none of them.
The company further writes that it has received an exclusivity payment concerning a potential development and sale of one of its larger data-centre projects. Which project, in which country, how large the payment is and who the counterparty is are not stated. Magnora Data Center has projects in Norway, Sweden, Finland, Estonia and Italy.
In Hylte, no investment decision has been taken. The grid installation is being designed with the regional network owner E.ON and requires a network concession, and the municipality expected the permit to gain legal force at the end of November. No grid capacity or connection date has been published.
Why it matters
Magnora is marketing its Swedish sites to investors, and a permitted site is what it sells. If the 85 MW permit is Hyltebruk, the company describes the site with a higher figure than the one in the municipal decision. If it is another site, a permit exists that no municipality has published.
Background
Magnora Data Center ASA is an Oslo-based developer that secures land, grid and permits to take sites to ready-to-build. Magnora ASA owns 52 percent of it. The Swedish business is run through Magnora Data Center AB, 67 percent owned by Magnora Data Center ASA. In Hyltebruk the permit covers a main building of about 14,000 square metres and 48 EPOD units with backup generators.
The power figure in context
60 MW ranks number 7 among the 20 projects in the register that publish a figure. The figures are of different kinds and must not be added together.
| EdgeConneX Skellefteå | 1,000 MW |
|---|---|
| Panattoni data centre, Hässleholm Nord | 300 MW |
| atNorth SWE04 Sollefteå | 300 MW |
| EcoDataCenter Borlänge | 250 MW |
| EcoDataCenter Smedjebacken (Röbacken) | 150 MW |
| Fossefall AI factory, Jokkmokk | 65 MW |
| Data centre, Hylte (Hyltebruk, Västra Åkralt) | 60 MW |
Questions that remain
- Which site does the 85 MW permit cover? The update names neither municipality nor property, and the only published Magnora permit gives about 60 MW.
- Is 85 MW IT capacity or total power? The Hylte minutes speak of installed IT capacity, while the update gives no metric.
- Which project does the exclusivity payment concern, and in which country? The company states neither project, amount nor counterparty.
- How far has the Säffle project come? The update only says it has been added, and no municipal decision is published in the register.
- Has the Hylte permit gained legal force? The municipality expected legal force at the end of November, but no notice has been published.
What remains unknown
Which site the 85 MW permit covers, what kind of megawatts the figure is, which project the exclusivity payment concerns and who paid it, and where the Säffle project stands with the municipality are not stated.
How the project has developed
- 2026-11-24Green Party interpellation on the Hyltebruk data centre is listed at Hylte's council; answer due in December
- 2026-11-23Magnora reports a building permit for an 85 MW data centre in southern Sweden, without naming the site
- 2026-11-12Hylte and Magnora set out next steps: E.ON grid, county permit, operation around 2029
- 2026-10-21Hylte grants building permits for a data centre and receiving station in Hyltebruk
Sources
- Magnora Data Center ASA — “Update on project progress and commercial traction” (NTB, 23 November 2026) — Magnora Data Center ASA / NTB, 2026-11-23. Checked 2026-11-24.
- Magnora Data Center ASA — “Update on project progress and commercial traction” (announcement PDF, 23 November 2026) — Magnora Data Center ASA / NTB, 2026-11-23. Checked 2026-11-24.
- Hylte municipality: minutes of the community-development committee (Samhällsbyggnadsnämnden), 21 October 2026, items 90 and 91 — Hylte kommun, 2026-10-29. Checked 2026-11-13.
- Hylte municipality: “Information om planerat projekt: Datacenter i Hyltebruk” (news item, 12 November 2026) — Hylte kommun, 2026-11-12. Checked 2026-11-13.
- Magnora Data Center ASA, Third quarter 2026 report (PDF, dated 29 October 2026) — Magnora Data Center ASA / NTB, 2026-10-30. Checked 2026-10-30.
- Magnora Data Center: Company portfolio — Magnora Data Center ASA, 2026-10-30. Checked 2026-10-30.