NewsPublished 2026-11-24 · Event 2026-11-24 · The editorial team

Hylte opposition demands answers on power, heat and funding for the data centre

The Green Party in Hylte has submitted an interpellation on the planned data centre in Hyltebruk, with fourteen questions on power, climate goals, waste heat, funding and jobs. The chair of the municipal executive board is to answer in December. Who finances the project is still not stated.

Bahnhof Bunker, Gothenburg — Under constructionPanattoni data centre, Hässleholm Nord — ProposedTherma Loop data centre, Halmstad (Kistinge) — ProposedSunSpark data centre, Gotland (Visby) — ProposedMagnora data centre, Tranemo (Limmared) — ProposedSunSpark data centre, Torsås (Söderåkra) — ProposedMagnora data centre, Hultsfred (Nyhagen) — ProposedMicrosoft Staffanstorp — OperationalBahnhof Sparven — OperationalGleSYS Falkenberg — OperationalHylte100 km
Data centre, Hylte (Hyltebruk, Västra Åkralt). The position is approximate.

The Green Party (Miljöpartiet) in Hylte has submitted an interpellation to the municipal council on the planned data centre on Västra Åkralt 1:80 in Hyltebruk. It is dated 19 November and listed among incoming interpellations at the council meeting on 24 November. The party addresses the chair of the municipal executive board, and asks fourteen questions on energy use and climate impact, the municipality's handling of the case, financing and jobs.

What is new is that the project is now raised in the council. In the municipality's published papers it has so far been handled as building-permit cases in the community-development committee. Hylte's community-development committee granted the building permit on 21 October for a data centre the applicant describes as designed for about 60 MW of installed IT capacity. The permit holder is Magnora Data Center AB with subsidiaries. The party writes that it does not question that the permit was handled correctly under the Planning and Building Act, but that the issue is too large to be reduced to a single building-permit case.

On power, the party cites E.ON's network development plan, where Hylte is marked as an area where further capacity measures are needed, and asks how the municipality views possible conflicts over electricity supply to existing and new industries that create more jobs per MW. It also asks whether the municipality has discussed with Magnora investments in new renewable generation matching the facility's use, and how backup power can be produced without climate emissions. The permit minutes describe 48 backup generators with diesel engines.

On heat, the party asks what Magnora's offer of waste heat for district heating at cost price means compared with what the municipality pays for district heating today. A second Green Party interpellation on the same agenda, on the follow-up of the energy and climate plan, asks how a new data centre affects the possibility of district heating.

On money, the interpellation asks what the municipal leadership has been told about the total cost of building the data centre and about Magnora's investors and customers. On jobs, it asks what the figures of 300 jobs during construction and 100 in operation are based on. Magnora's own information sheet for Hyltebruk gives about 300 to 400 full-time posts in the most intensive construction phase and up to about a hundred people on site in operation.

The party also criticises the timing. The permit was published as a notice on 29 October, while the municipality's broad news item came on 12 November. The four-week appeal period runs from 29 October, which according to the party gives little time to anyone who learned of the project on 12 November.

According to SVT Halland, the chair of the municipal executive board (S) will answer in the council in December; the council's next listed meeting is on 15 December. In a text message to SVT he wrote that the municipality granted a building permit on private land and has no control over a possible establishment, and that the issue needs to be looked at if Magnora takes an investment decision.

Why it matters

The permit is close to legal force, so the building-permit route offers little more leverage. The interpellation moves the questions the permit did not have to answer, on grid capacity, backup fuel, heat price and funding, into the council. The answer in December will be the municipal leadership's first public position on them.

Background

An interpellation is a formal question from a councillor to the chair of a committee, answered in the council with a debate but no decision. Hylte's permit covers a main building of about 14,000 square metres and 48 EPOD units with backup generators. According to the permit minutes, noise at the nearest home is modelled at 39 dB(A) at maximum operation and at most 49 dB(A) with the backup generators. The municipality and the company said on 12 November that no investment decision has been taken.

The power figure in context

60 MW ranks number 7 among the 20 projects in the register that publish a figure. The figures are of different kinds and must not be added together.

Published power by project, MW
EdgeConneX Skellefteå1,000 MW
Panattoni data centre, Hässleholm Nord300 MW
atNorth SWE04 Sollefteå300 MW
EcoDataCenter Borlänge250 MW
EcoDataCenter Smedjebacken (Röbacken)150 MW
Fossefall AI factory, Jokkmokk65 MW
Data centre, Hylte (Hyltebruk, Västra Åkralt)60 MW

Questions that remain

  • Has the building permit been appealed? The municipality expected legal force at the end of November, and no notice of legal force or of an appeal has been published.
  • Who finances the data centre and who will be the customer? The company has not named investors or an end customer, and the interpellation asks what the municipal leadership has been told.
  • What will the waste heat cost? The company speaks of cost price, but no figure or comparison with today's district-heating cost is published.
  • Which fuel will the backup generators use? The minutes describe diesel engines while the company has described fossil-free backup power, and the county board has not yet examined the operation.
  • Is the grid in Hylte enough? The interpellation points to E.ON's capacity warning, but no grid capacity, connection agreement or connection date is published.

What remains unknown

Whether the permit has been appealed, what the municipal leadership knows about Magnora's investors, customers and total cost, what the cost-price heat offer would mean in kronor, and which fuel the backup generators will use are not stated.

How the project has developed

  1. 2026-11-24Green Party interpellation on the Hyltebruk data centre is listed at Hylte's council; answer due in December
  2. 2026-11-23Magnora reports a building permit for an 85 MW data centre in southern Sweden, without naming the site
  3. 2026-11-12Hylte and Magnora set out next steps: E.ON grid, county permit, operation around 2029
  4. 2026-10-21Hylte grants building permits for a data centre and receiving station in Hyltebruk

Every event and source in the register