RoundupPublished 2026-11-18 · Event 2026-11-17 · The editorial team

Over 5,000 sign against EdgeConneX in Skellefteå as neighbours fear noise

A petition against EdgeConneX's planned data centre on the former Northvolt site in Skellefteå has passed 5,000 signatures. Neighbours in Bergsbyn fear noise, and the company's consultation documents describe new noise sources. A study of the combined noise with Lyten's factory has not yet been done.

Arcem data centre, Strömsund (Hoting) — ProposedFossefall AI factory, Jokkmokk — In developmentRoofscapes data centre, Bräcke — AnnouncedMeta Luleå — OperationalatNorth SWE04 Sollefteå — In developmentHydro66 Svenska, Boden — OperationalSkellefteå100 km
EdgeConneX Skellefteå. The position is approximate.

SVT Västerbotten reported on 17 November 2026 that residents of Bergsbyn, a few hundred metres from EdgeConneX's planned data centre in Skellefteå, are worried about noise. According to SVT, the company's consultation documents for the County Administrative Board state that the data-centre operation will mainly emit noise from coolant coolers, ventilation and backup generators run once a month, and that it will mean a changed noise situation for people living nearby. A noise study that weighs together the noise from EdgeConneX and from Lyten's battery factory on the same site is to be carried out.

What is new compared with the register is the opposition and the noise question. So far the register has followed the formal steps: the building permit of 24 September for the first two buildings and, according to Norran, the partial start notice for foundations on 29 October. The petition on the campaign site MittSkifte demands that Skellefteå's municipal council and the County Administrative Board of Västerbotten say no to further building and operating permits, and that the site's power and infrastructure go to industry instead. The site states that 5,000 signatures have been reached. When SVT reported from the first consultation on 6 November, about 4,000 had signed; Sveriges Radio's Ekot reported 5,000 on 12 November. The organisers write that they chose not to hand over the list at the consultation meeting on 5 November because it is better suited to be submitted later.

The petition argues that the data centre could use as much power as a whole city, up to 1,000 MW, that this risks pushing up electricity prices, that diesel backup generators would run if the grid is insufficient, and that claims of 400 to 1,000 jobs are misleading because most would be temporary construction jobs. EdgeConneX's head for Europe, the Middle East and Africa told SVT that what the company builds will meet the permit requirements for noise. On electricity prices he referred to Skellefteå Kraft.

The municipality answers the criticism on a questions-and-answers page. Its assessment is that the establishment should not have any significant effect on electricity prices in a normal weather year, and that Skellefteå Kraft has assessed that delivery security, grid stability and network tariffs for existing customers will not be affected. The municipality writes that the cooling technology in question is closed water cooling without evaporation, and that EdgeConneX states construction will employ about 1,000 people. The page does not give a number of permanent jobs.

The power figures need to be read in proportion. SVT cites Dagens industri as reporting that the fully built data centre could use 9.2 TWh a year, against Skellefteå Kraft's total electricity production of 4 TWh in 2025. Spread evenly over a year, 9.2 TWh corresponds to an average load of about 1,050 MW, the top of the range of seven buildings at 96 to 150 MW each, 672 to 1,050 MW, that SVT earlier reported from the consultation documents. EdgeConneX's own potential figure of up to one gigawatt is the largest published power figure among the projects in the register. None of these figures is a contracted grid capacity.

This is a roundup of what media and the parties have reported. The register's facts on the project do not change; the entry now notes the petition and the pending noise study.

Why it matters

Phase one so far only has a partial start notice for the foundations. The steps that remain, the full start notice and the consultation with the County Administrative Board on how the operation is to be permitted, are where noise and backup power are examined, and they are the steps the petition targets. The noise study will be the first document to present the noise from the data centre and the battery factory together.

Background

Northvolt's battery factory at Bergsbyn went bankrupt. According to the municipality, Lyten bought the land from the bankruptcy trustee in February 2026, and EdgeConneX later the same year acquired parts of the area for its planned data centre. According to SVT, Lyten plans to make batteries on about half of the former Northvolt site. EdgeConneX's first phase, DC01 and DC02, is planned to be complete in 2028 according to SVT; the consultation documents describe five more buildings by early 2031.

The power figure in context

1000 MW ranks number 1 among the 20 projects in the register that publish a figure. The figures are of different kinds and must not be added together.

Published power by project, MW
EdgeConneX Skellefteå1,000 MW
Panattoni data centre, Hässleholm Nord300 MW
atNorth SWE04 Sollefteå300 MW
EcoDataCenter Borlänge250 MW
EcoDataCenter Smedjebacken (Röbacken)150 MW
Fossefall AI factory, Jokkmokk65 MW
Data centre, Hylte (Hyltebruk, Västra Åkralt)60 MW

Questions that remain

  • Will the data centre meet the noise guideline values at the homes in Bergsbyn? The combined noise study with Lyten's factory has not been done, and without it the company's promise to meet the permit requirements cannot be assessed.
  • Does the operation require an environmental permit, and who examines it? The consultation with the County Administrative Board is ongoing, and the type of review it leads to decides where the petition's demand can matter. The sources do not say which route it will be.
  • How much power is contracted for the site? EdgeConneX is taking over Northvolt's former connections, but the contracted capacity is not disclosed, and 9.2 TWh is a full build-out figure, not an agreement.
  • How many permanent jobs will there be? The municipality cites the company's figure of about 1,000 people during construction but gives no number for operations, while the petition calls the job claims misleading.
  • When and to whom will the list be submitted? The organisers chose not to hand it over at the consultation meeting on 5 November and have not said when that will happen.

What remains unknown

The results of the noise study, whether the operation will require an environmental permit, the contracted grid capacity for the site, the number of permanent jobs, and when and to whom the petition will be submitted are not known.

How the project has developed

  1. 2026-10-29Skellefteå issues partial start notice for EdgeConneX foundations
  2. 2026-09-24Skellefteå grants building permit for EdgeConneX's DC01 and DC02