Uppsala County

Uppsala County enters the register with one proposed project: a data centre on municipal land at Ullunda in Enköping. On 30 September 2026 Enköping's planning, land and development committee started a development project for the site up to the adoption of a detailed plan. The developer is not named and no power capacity is given.

The documented decision is item 93 of the committee's minutes of 30 September 2026, case KS2026/829. The committee writes that there is a great need for data centres and strong demand in the Mälardalen region.

Enköping's municipal energy company ENA Energi is working on an agreement with Conapto in two parts, a cooperation agreement and a delivery agreement, expected to be finished in early 2027. The municipal documents do not link it to the Ullunda site.

Documented projects in the register

Questions for a concrete establishment

  • Does Enköping grant a positive planning decision for Ullunda 8:1>2?
  • Who is the developer, and what power capacity is sought?
  • Does the county administrative board accept data-centre use of the farmland?

Related news

Sources