Kalmar County

Kalmar County enters the register with one proposed project: a data centre in the Nyhagen industrial area in Hultsfred. On 1 September 2026 Hultsfred's municipal executive committee approved a letter of intent with Magnora Project Infra 2 AB on investigating it. No land sale has been decided and no power capacity is given.

The documented decision is item 108 of Hultsfred's executive committee minutes of 1 September 2026, case 2026/208. The minutes say data-centre requests to the municipality have risen sharply over the past 12 to 18 months, with at most five at the same time.

The municipality will not consider a land sale that uses grid capacity until the effects on existing businesses, the project's feasibility and the local benefit are verified. Grid capacity, investment and timetable are not public.

Documented projects in the register

Questions for a concrete establishment

  • Does Hultsfred's working committee approve step 1 of the letter of intent?
  • What grid capacity can E.ON offer at Nyhagen, and when?
  • Does a land sale reach the municipal council?