Sites for data centers in Sweden

Land for data centers that we have reviewed in the public material of municipalities and landowners. Each site has a readiness level that follows from what can be confirmed about planning, power and land. The place, the owner and the sources are in the site file, which you get by e-mail.

Sites marked Public sources are compiled without an assignment from the landowner. We have not checked with the owner that the land is free, and what could not be confirmed is shown as unknown.

Available sites

Readiness level
ConfirmedElectricity area

Loading map…

12 of 12 sitesHighest level first

Circles show an approximate area, not the property. A darker circle means a higher readiness level. Grey dots are projects in the register.ConfirmedPartlyUnknown

How the readiness level is set

The level is not our opinion. It follows from which facts are confirmed by documents we have checked. What is not confirmed is shown as unknown.

  1. 1DesignatedThe municipality, landowner or network owner has designated the site. Neither plan nor power is confirmed.
  2. 2Plan or power in placeEither a detailed plan in legal force or a statement from the network owner is confirmed.
  3. 3Plan and power in placeBoth a detailed plan in legal force and a statement from the network owner are confirmed.
  4. 4Ready to buildPlan, power and available land are all confirmed.

Do you have suitable land?

Municipalities, landowners and representatives can submit a site. We review the evidence before anything is published, and you decide what may be shown.

Submit a site

The sites are separate from the editorial project register. DataCenterSweden introduces interested parties to the landowner. Ownership and commercial relationships