2026-09-10
Sweden Data Center Briefing — September 2026
First archived monthly note. It records material public changes already captured in the project register. It is not a forecast and not a complete market census.
atNorth ownership notice
On 2 September 2026 atNorth said CPP Investments and Equinix completed an acquisition. Swedish site stages in this register are unchanged.
Read moreFalun capacity series
EcoDC’s 2025 report is the dated source for 41 MW after C and D, with 65 MW described as a later campus total if E and F enter operation.
Read moreArlandastad still in development
evroc’s February 2025 land notice remains the latest primary source used here. Operation in H2 2026 was a company expectation, not a verified outcome in this file.
Read moreBidding-area review is political work, not spare MW
The government expanded Svenska kraftnät’s bidding-area assignment in May 2026, with reporting due 29 January 2027. That is not a site-level connection answer.
Read more