Jokkmokk study: Fossefall's data hall could heat the town, but the heat price is open
A feasibility study for Jokkmokk's district heating names waste heat from Fossefall's planned data hall as the main option, with an 8 MW heat pump and a seven-year payback. The calculation assumes the heat comes free or cheap. The commercial terms have not been agreed.
A feasibility study on district heating in Jokkmokk names waste heat from Fossefall's planned data hall as the main option. According to the study, an 8 MW heat pump recovering heat from a data centre would be cost-effective, with a payback time of seven years including the pipework. The municipality reported the study on 12 November, and today the trade magazine Tidningen Energi writes about it.
What is new is that the data hall now features in the planning of the municipal energy company, Jokkmokks Energi. Until now the register only held Fossefall's own statements: the grid connection agreement with Vattenfall Eldistribution for 65 MW announced on 10 November, and a possible expansion to 200 MW in total. Nothing on the heat.
The study was carried out by IBF Expertise and Energy Modelling Lab for Energikontor Norr and Region Norrbotten, in cooperation with EIB Advisory, and was financed by the European Investment Bank. In Jokkmokk the heat pump is combined with a 100 MWh accumulator tank and a 3 MW electric boiler to cover peaks. The existing oil boilers (11 MW) are kept as backup. The heat pump's annual average efficiency (COP) is put at 12.6 in Jokkmokk, against 1.96 for the air-source heat pump in Arvidsjaur, the comparison town, where the payback time is over 15 years.
According to the study, the data centre can supply more waste heat than the town needs. Jokkmokk's district heating is currently fired with biomass. According to Tidningen Energi the network has about 550 customers, and new processor technology can give waste heat at about 60–65 degrees, which the heat pump then raises.
The catch is the price. Tidningen Energi writes that the calculation assumes the waste heat is supplied at no or little cost, because the commercial terms have not been set. The study says the solution is cost-effective provided both parties can agree on the value of the waste heat. The municipality and the study both point to the dependence on an outside supplier: the network still needs backup capacity for when the data hall does not deliver.
The next step is to seek funding for a more detailed feasibility study and design work. Only after that could an investment decision become relevant, according to Tidningen Energi. Nor has Fossefall taken a final investment decision; construction is expected to start in the second quarter of 2027.
The figures for the data hall differ between sources. In May 2026 Fossefall described an initial phase of about 45 MW. Tidningen Energi now gives about 65 MW for a first phase, the same figure as the grid agreement. According to the magazine, the data hall is planned together with the company Ållojaure Sites. The register has a comparable case in Sollefteå, where atNorth and Calentix plan heat from SWE04 to the Långsele network, with 1.6 MW in a first phase and a heat purchase agreement targeted for 2027.
Why it matters
It is the first time a heat buyer is described for the Jokkmokk data hall. For Jokkmokks Energi the waste heat could replace much of the biomass, but the payback rests on a heat price that has not been negotiated, and on a data hall without a final investment decision.
Background
Fossefall plans an AI factory, a data centre with GPU compute, on a 350,000-square-metre site in Jokkmokk planned for industrial use, in bidding area SE1. In May 2026 the company described a platform of up to 200 MW. On 10 November 2026 it announced a grid connection agreement with Vattenfall Eldistribution securing 65 MW, with the potential for a further 135 MW.
The power figure in context
65 MW ranks number 6 among the 20 projects in the register that publish a figure. The figures are of different kinds and must not be added together.
| EdgeConneX Skellefteå | 1,000 MW |
|---|---|
| Panattoni data centre, Hässleholm Nord | 300 MW |
| atNorth SWE04 Sollefteå | 300 MW |
| EcoDataCenter Borlänge | 250 MW |
| EcoDataCenter Smedjebacken (Röbacken) | 150 MW |
| Fossefall AI factory, Jokkmokk | 65 MW |
| Data centre, Hylte (Hyltebruk, Västra Åkralt) | 60 MW |
Questions that remain
- What will the waste heat cost? The calculation assumes the heat is supplied free or cheaply, and the commercial terms have not been set.
- Has Fossefall committed to supplying heat? The information comes from the energy company, the municipality and the study, not from Fossefall.
- Is the first phase 45 or 65 MW? Fossefall gave about 45 MW in May, and Tidningen Energi now gives about 65 MW.
- Who pays for the heat pump and the pipework? The next step is to seek funding, and there is no investment decision.
- What role does Ållojaure Sites have? The company is named as a partner, but the sources do not describe its task.
What remains unknown
What the heat will cost, whether Fossefall has committed to supply it, who finances the heat pump and the pipework, when a heat agreement could be signed, and what role Ållojaure Sites has are not stated.
How the project has developed
- 2026-11-12Feasibility study: waste heat from Fossefall's data hall could supply Jokkmokk's district heating
- 2026-11-10Fossefall signs grid connection agreement with Vattenfall Eldistribution for 65 MW in Jokkmokk
Sources
- Jokkmokk Municipality — “Restvärme kan bli en del av Jokkmokks framtida fjärrvärme” (news, last updated 12 November 2026) — Jokkmokks kommun, 2026-11-12. Checked 2026-11-23.
- Energikontor Norr — “Värmepumpar i fjärrvärmen: förstudie för Arvidsjaur och Jokkmokk” (EIB Advisory / TARGET, article PDF, October 2026) — Energikontor Norr, 2026-10-27. Checked 2026-11-23.
- Tidningen Energi — “Jokkmokk utvecklar framtidslösning för fjärrvärmen” (23 November 2026) — Tidningen Energi, 2026-11-23. Checked 2026-11-23.
- Fossefall: Fossefall secures grid capacity for AI factory in Jokkmokk (10 November 2026) — Fossefall, 2026-11-10. Checked 2026-11-10.
- Fossefall moves into Sweden with a Jokkmokk AI-infrastructure platform — Fossefall, 2026-05-08. Checked 2026-09-12.