NewsPublished 2026-11-17 · Event 2026-11-01 · The editorial team

Svenska kraftnät's data-centre queue reaches 8,200 MW; the rise is almost all in SE3

Applications for data-centre connections in Svenska kraftnät's transmission-grid queue rose to 8,200 MW as of 1 November 2026, from 7,326 MW a month earlier. The authority's table by electricity area puts the increase in SE3. Who applied is not published.

Generic server image for context; it does not depict any facility in Svenska kraftnät's queue.
Generic server image for context; the queue table names no applicants. Photo Đào Hiếu on Unsplash

Svenska kraftnät's queue for connection to the transmission grid held applications for 8,200 MW of data-centre load on 1 November 2026, according to the authority's statistics page, last reviewed on 10 November. The snapshot a month earlier, as of 1 October, showed 7,326 MW. The increase is roughly 870 MW, or about 12 per cent. Between the September and October snapshots the row grew by 342 MW.

What is new is where the increase sits. The authority's table by electricity area lists 6,000 MW of data-centre applications in SE3, 1,650 MW in SE2 and 500 MW in SE1. SE4 has none. In the October version of the same table, preserved in an archived copy, SE3 stood at 5,169 MW, SE2 at 1,662 MW and SE1 at 495 MW. SE1 and SE2 are essentially unchanged; SE3 has risen by just over 800 MW. SE3 had also been at 5,169 MW in the September table, so the October growth was in SE2 and the November growth is in SE3.

The November figures are rounded to the nearest 50 MW, which the authority states under the table; the October figures were exact. That is why the electricity areas add up to 8,150 MW while the national row shows 8,200 MW, and why the monthly changes can only be given approximately, with a margin of around 25 MW per cell.

Requested capacity is not consumption. Svenska kraftnät counts an application in the table until capacity has been reserved and a preliminary notice (förhandsbesked) has been sent. The 8,200 MW is therefore an application-stage measure, not reserved capacity, a signed connection agreement or power that new sites can count on. The table names no applicants and does not show which projects are behind the increase.

In proportion, data centres now account for 6,000 of the 10,250 MW of consumption applications in SE3, close to six megawatts in ten. Nationally the data-centre row is 8,200 of 26,700 MW of consumption applications; industry is still the largest category at 14,200 MW, of which 10,950 MW is in SE1. At the same time, the industry row in SE3 fell from 1,568 to 1,150 MW. The table does not say whether any application has moved between categories.

The snapshot is dated two days before Svenska kraftnät said on 3 November that it is considering temporary restrictions in how it handles applications for large individual withdrawals, including large data centres. The November figure therefore does not show how the queue has reacted to that announcement. If the authority keeps its monthly rhythm, the next snapshot will show the position on 1 December.

Why it matters

SE3 is now where demand for new data-centre connections is concentrated: almost three quarters of the data-centre row is there. If Svenska kraftnät introduces temporary restrictions on large individual withdrawals, applications of this kind are the ones it has said it is looking at, and a rise of about 800 MW in one month in one electricity area shows why the question is pressing.

Background

Svenska kraftnät owns and operates the national transmission grid. Large consumers and regional network owners apply to it for connections, and the authority publishes a monthly snapshot of requested capacity by connection type, excluding offshore wind, which is handled separately. DataCenterSweden has followed the data-centre row since the 1 September 2026 snapshot, when it stood at 6,984 MW.

Questions that remain

  • Who is behind the increase in SE3? Svenska kraftnät publishes no applicants, so the roughly 800 MW cannot be tied to known projects in the register.
  • Are these new applications or reclassifications? The industry row in SE3 fell by just over 400 MW in the same month, and the table does not explain the changes case by case.
  • How much of the queue can get capacity? The table only shows applications before reservation and says nothing about what share usually goes on to a preliminary notice or agreement.
  • Would any restrictions cover applications already in the queue? The authority has not said, and the answer decides whether the November figure is a ceiling or a starting point.

What remains unknown

The applicants, the projects and sites behind the increase, the size of individual applications, whether any applications were reclassified from industry, and how many of the applications will be reserved, granted or energised are not published.