NewsPublished 2026-11-26 · Event 2026-11-19 · The editorial team

evroc and Telia Cygate launch a public-sector cloud, run from Telia's data centres

evroc and Telia Cygate presented Government Cloud on 19 November, a cloud for the public sector's most critical operations. evroc owns the software; Telia Cygate supplies security-classified data centres, GPU capacity and operations. Launch is expected in the first half of 2027. Which data centres and how much capacity are not stated.

In short

  • Government Cloud is to run in Telia's security-classified data centres with security-cleared staff. No site is given.
  • evroc's own flagship in Arlandastad is not mentioned, and the company still gives no opening date for it.
  • Launch is planned for the first half of 2027, ordered through Telia Cygate's framework agreement with Kammarkollegiet.
  • The cloud should be able to use the AI infrastructure Telia's consortium plans in Sweden.
Aerial view of Arlandastad in Sigtuna municipality with motorways, car parks, a large retail building and a golf course in autumn colours.
Arlandastad in Sigtuna municipality from the air, October 2017. evroc is building its flagship data centre in Arlandastad, but the Government Cloud releases do not mention the site; the photo does not show evroc's building. Cropped and resized. Photo I99pema, Wikimedia Commons, CC BY-SA 4.0

What is being launched

evroc and Telia Cygate presented Government Cloud on 19 November, a cloud for the public sector's most critical operations. Both companies describe it as Sweden's first sovereign cloud for the public sector.

The roles are split. evroc builds, owns and controls the software platform. According to evroc, Telia Cygate provides the physical base: secure, security-classified data centre sites, staffed by security-cleared personnel and connected to Telia's national fibre network. Telia Cygate is also to supply dedicated GPU capacity for AI, operations and hardware. According to Telia Cygate, the staff are also earmarked for wartime posts.

What is new: Telia's data centres, not evroc's own

Telia Cygate writes that the platform will use Telia's infrastructure, including security-classified data centres, and that it already delivers operations services from Swedish data centres connected to Telia's network. No site, municipality, power figure or GPU count is given.

evroc's own flagship in Arlandastad is not mentioned. The company's data-centres page, read on 26 November, says the facility is being built, with room for up to 10,000 GPUs, but gives no opening date. In February 2025 evroc expected operations in the second half of 2026 and stated 18 MW, without saying what kind of power that is. The same page says evroc now has its own data centres under construction in Stockholm and Mougins and partner data centres in Paris, Stockholm and Frankfurt.

evroc Arlandastad among the register's projects in the county

Published power in the register for the largest projects and the projects in this article. evroc Arlandastad: number 4 of 8.

evroc Arlandastad among the register's projects in the county
ItemMW
atNorth SWE02 Akalla (site power)30
Conapto Stockholm South (site power)24
Stendörren data centre, Södertälje (Almnäs) (utility power)20
evroc Arlandastad (announced capacity (definition unclear))18
STACK STO01 Stockholm (announced capacity (definition unclear))18
atNorth SWE01 Kista (site power)12

The figures are of different kinds (site, IT or unclear power) and must not be added together.

Source: the DataCenterSweden register, where every figure has its own source.

The link to the AI gigafactory

According to Telia Cygate, Government Cloud should also be able to use the AI infrastructure planned in Sweden within the European consortium Telia is part of. The consortium is not named. On 16 November Telia, Nokia, Nscale, Verda and Skeleton announced that they had formed AI Gigafactory Northern to bid in the EU procurement of AI gigafactories, with a Swedish site not yet chosen.

When and how

A commercial launch is planned for the first half of 2027. Public bodies are to be able to order the service through Telia Cygate's framework agreement with Kammarkollegiet (the Legal, Financial and Administrative Services Agency) and, according to evroc, through other approved procurement routes. evroc says the cloud is built to deliver on the EU Cloud Sovereignty Framework. According to Telia Cygate, evroc already works with the Swedish Armed Forces on the sovereign cloud platform SINCC.

evroc's chief executive points to the interest the company is seeing, but no customer or agency is named.

Why it matters

According to the companies, demand for secure, nationally controlled capacity for public-sector data and AI is to be met in Telia's existing security-classified data centres, not in a new named hall. For the register, this means a new public-sector cloud service cannot be tied to a site or a power figure, and evroc's own build in Arlandastad still has no opening date.

Timeline

  1. 3 February 2025evroc reports completed land purchase in Arlandastad [4]
  2. 20 October 2026evroc now states up to 10,000 GPUs for Arlandastad [6]
  3. 16 November 2026Telia, Nokia, Nscale, Verda and Skeleton form AI Gigafactory Northern, Swedish site not chosen [5]
  4. 19 November 2026evroc and Telia Cygate present Government Cloud; Telia's classified data centres named as the physical base, Arlandastad not mentioned [1]
  5. 26 November 2026evroc's data-centres page: the flagship is still being built, no opening date [3]

What we do not know yet

  • Which data centres, and in which municipalities, Government Cloud will run in.
  • How much GPU capacity and power is set aside.
  • Whether evroc's Arlandastad facility will be used, and when it opens.
  • Which public bodies have shown interest or will place orders.
  • Which consortium Telia Cygate means, and where its Swedish facility would be.

Questions that remain

  • Where are the servers? Telia Cygate speaks of security-classified data centres connected to Telia's network but names no site or municipality.
  • How much capacity is involved? evroc writes that Telia Cygate will supply dedicated GPU capacity for AI, but no figure for GPUs or megawatts is given.
  • What does it mean for Arlandastad? evroc expected operations there in the second half of 2026, but the releases do not mention the facility and the page gives no date.
  • Who are the customers? evroc points to interest, but no agency is named and orders can only be placed once the service launches in 2027.

Sources

  1. evroc — “evroc and Telia Cygate launch Government Cloud, first sovereign national cloud for Sweden's public sector” (press release, 19 November 2026) — evroc, 2026-11-19. Checked 2026-11-26.
  2. Telia Cygate — “Telia Cygate och evroc lanserar Sveriges första suveräna moln för offentlig sektor” (press release, 19 November 2026) — Telia Cygate, 2026-11-19. Checked 2026-11-26.
  3. evroc — Data centers (company page, read 26 November 2026) — evroc. Checked 2026-11-26.
  4. evroc finalizes land purchase in Arlandastad, Stockholm — evroc, 2025-02-03. Checked 2026-10-21.
  5. Telia Company press release: Telia and European technology leaders form AI Gigafactory Northern, a consortium to build reliable and sustainable AI infrastructure (16 November 2026) — Telia Company (Cision), 2026-11-16. Checked 2026-11-16.
  6. evroc: Data centers — evroc. Checked 2026-10-20.