Published 2026-09-12 · Event 2026-03-26 · The editorial team

Stockholm’s Akalla 4:8 minute is a Chapter 9 referral, not a 100 MW permit

An industrial interior with equipment carts and overhead pipework.
An industrial interior with equipment carts and overhead pipework. Photo Lawrence Krowdeed on Unsplash

On 26 March 2026 Stockholm’s Exploitation Committee approved a notification that the city would answer a consultation before a Chapter 9 Environmental Code application for a data centre and a combustion plant, total installed capacity 100 MW, on property Akalla 4:8. Approving a referral answer is not a permit.

The Exploitation Committee extract from 26 March 2026, §11, file E2026-00455, is the dated municipal source used here. The item is titled as an invitation to consultation before an application for a permit under Chapter 9 of the Environmental Code for a data-centre activity and a combustion plant, total installed capacity 100 MW, on property Akalla 4:8. The decision is that the committee approves the notification of a referral answer. The supporting paper is the Exploitation Office statement of 3 March 2026. A committee approval of a notification is not a Chapter 9 permit.

The megawatt sentence must stay an application-scope sentence. One hundred megawatts is the total installed capacity printed in the minute for the described activity. It is not a reserved grid offtake, not a commissioned hall and not a named operator campus. The minute does not name a tenant, a network agreement or a construction start.

The heat-and-station neighbours must stay neighbours. Stockholm’s earlier Akalla heat-recovery planning page and Ellevio’s indoor distribution station at Raseborgsgatan are different dates and different legal rows. This article does not merge a Chapter 9 referral with a station build or a heat-recovery invitation, and it does not attach a project identifier to the property number.

Related grid notes stay on their own pages. Ellevio’s 2025 year-end sentence about two Akalla data-centre connection agreements, the SWE02 heat note and Ellevio’s Stockholm regional-network snapshot are different issuers. This article does not import those rows into a 26 March committee minute.

DataCenterSweden records 26 March 2026 as a Stockholm Exploitation Committee referral notification for Akalla 4:8. No project identifier is attached. The next update would need a later primary source that names a Chapter 9 decision, a reserved offtake or a commissioned plant on the property. Until then, 100 MW stays the printed application scope — not a granted Stockholm hall permit.

Why it matters

A City of Stockholm minute that prints 100 MW and the word data centre is easy to file as a granted Akalla campus. The March extract is usable only if the referral stays a referral — not a permit.

What remains unknown

The minute does not decide the Chapter 9 application, name an operator or attach a reserved grid offtake to Akalla 4:8.

Sources

  1. Stockholm Exploitation Committee minutes 26 March 2026, §11 (E2026-00455) — Akalla 4:8 referral — Stockholms stad / Insyn Sverige, 2026-03-26. Checked 2026-09-12.