Published 2026-09-12 · Event 2026-05-28

Svenska kraftnät’s Horndal station line works are connecting-bay construction, not reserved Dalälven hall power

Construction cranes above a generic industrial building site.
Photo Sergej Karpow on Unsplash

Svenska kraftnät’s 28 May 2026 Horndal-station note says field works now start on the lines that will connect to the renewed 220 kV station in Avesta Municipality. Excavation and construction roads are not reserved offtake.

Svenska kraftnät’s 28 May 2026 line-works note is the dated Horndal-station source used here. It says renewal of the transmission station continues as planned and that construction of the lines that will connect to the new station now starts. Field works in the near term are excavation for foundations and construction roads. Those works are a prerequisite for raising poles and building the new lines. Connecting-bay construction is not a reserved offtake.

The timetable sentence must stay a timetable sentence. Pole assembly on the ground continues in the autumn and winter. Raising of the poles, together with stringing, is planned to start in March 2027. The Horndal-station hub writes a 220 kV station renewal in Avesta Municipality, construction start in 2025, commissioning in 2027 and project close-out in 2028. Those are programme dates. They are not reserved megawatts.

The contractor sentence must stay a contractor sentence. Station works are written as Linjemontage and the line works as Craftor, both on assignment from Svenska kraftnät. Named contractors are not a hall agreement.

Related grid notes stay on their own pages. The Horndal–Avesta 220 kV rebuild, Horndal–Munga, Fallviken–Horndal and Avesta’s earlier municipal plan paper at Horndal are different dates and different legal rows. This article does not import a Google campus name or a neighbouring 400 kV remittal into a Horndal-station line-works day.

DataCenterSweden records 28 May 2026 as a Svenska kraftnät connecting-line notice at Horndal station. No project identifier is attached. The next update would need a later primary source that names commissioned bays, a reserved consumption agreement beside the station or a hall offtake. Until then, the May works stay connecting-bay construction — not reserved Dalälven hall capacity.

Why it matters

A Horndal construction headline is easy to file as spare mid-Sweden hall power. The May note is usable only if the connecting-line works stay connecting-line works — not a reservation.

What remains unknown

The note does not commission the new station, reserve a consumption agreement or name a hall offtake beside Horndal.

Sources

  1. Construction continues, line works start at Horndal station Svenska kraftnät, 2026-05-28. Checked 2026-09-12.
  2. Horndal station — Svenska kraftnät project hub Svenska kraftnät, 2026-05-28. Checked 2026-09-12.