Published 2026-09-12 · Event 2026-02-05
Njutånger–Mehedeby’s February filing is a 150 km NordSyd pair, not the Tierp zoning paper

Svenska kraftnät’s 5 February 2026 note says a concession application for two new 400 kV lines between Njutånger and Mehedeby has been filed. A 150-kilometre rebuild through Gävleborg and Uppsala counties is not the Tierp Mehedeby plan-opinion.
Svenska kraftnät’s 5 February 2026 Njutånger–Mehedeby note is the dated filing source used here. It says a network-concession application has been sent to the Energy Markets Inspectorate for two new 400 kV lines between Njutånger and Mehedeby. A 220 kV line and a 400 kV line that have reached the end of their technical life are to be demolished as part of the same rebuild. A filing is not reserved offtake.
The geography sentence must stay a geography sentence. The printed facts say the stretch is about 150 kilometres and passes through Hudiksvall, Söderhamn, Gävle, Älvkarleby and Tierp. A new transmission station is planned at Njutånger. Where possible the lines follow existing rights-of-way. Passing through Tierp Municipality is a corridor fact. It is not the municipal Mehedeby plan-opinion for a data-centre investigation.
The timetable sentence must stay a timetable sentence. Consultation ran from April to September 2024, with a complementary Valbo consultation in the autumn. Inspectorate handling is expected in 2027. Construction is planned for 2029, with the new lines in service in 2034–2035. The same NordSyd package sentence that appears on the Vattjom–Njutånger note — about 100 billion kronor and a 7,300 MW to 10,500 MW transfer envelope between bidding areas 2 and 3 — stays a package sentence. It is not a reserved hall megawatt on this stretch.
Named neighbouring papers stay neighbouring papers. The Vattjom–Njutånger filing of the same morning, Tierp’s Mehedeby plan-opinion, Svenska kraftnät’s Mehedeby–Jälla sibling row in the Uppsala package and Ellevio’s Gävleborg snapshot stay on their own files. This article does not merge the 150-kilometre pair with a municipal zoning paper.
DataCenterSweden records 5 February 2026 as a Svenska kraftnät concession filing for Njutånger–Mehedeby. No project identifier is attached. The next update would need a later primary source that names a granted concession, a construction start or a reserved offtake beside the corridor. Until then, the 150-kilometre pair stays a NordSyd filing — not the Tierp Mehedeby zoning paper and not reserved hall capacity.
Why it matters
A Mehedeby 400 kV filing is easy to file as the Tierp data-centre zoning paper. The February note is usable only if this pair stays a NordSyd rebuild.
What remains unknown
The note does not print a granted concession, a reserved hall megawatt or a merger with the Tierp Mehedeby plan-opinion.
Sources
- Svenska kraftnät files for Njutånger–Mehedeby concession — Svenska kraftnät, 2026-02-05. Checked 2026-09-12.