Published 2026-09-12 · Event 2026-08-19

Svenska kraftnät starts construction of Munga 400 kV station

Construction cranes above a generic industrial building site.
Photo Sergej Karpow on Unsplash

An 19 August 2026 operator note says works in Västerås start in late August, with Koncar and NYAB as contractors. A station shovel start is not reserved Mälardalen hall offtake.

Svenska kraftnät's 19 August 2026 note on the Munga–Hamra current-affairs page is the dated source used here. The operator says construction of the new 400 kV station at Munga, in Västerås, begins in late August 2026. The named contractors are Koncar and NYAB. A station construction start is not reserved hall offtake, and it is not a concession paper for the connecting lines.

The printed timetable on that note puts line permit in June 2026, station works from August 2026 to 2028, and commissioning in December 2028. Those dates stay a timetable. Commissioning in 2028 is not energised offtake in 2026.

The same note says four new transmission lines and a Vattenfall Eldistribution regional station will connect when the station is finished. Those connections stay a when-finished sentence. They are not live circuits in August 2026, and they are not a named campus reservation.

Early works named on the page include tree felling, blasting, and road widening. Those civil verbs stay civil verbs. They are not a reserved megawatt figure.

DataCenterSweden records 19 August 2026 as the construction-start note. The June government papers on Munga–Hamra and Bysingsberg–Munga stay neighbouring legal-force papers, not this shovel-start row.

Why it matters

Mälardalen 400 kV reinforcement has moved from permit paper to a named station contractor start.

What remains unknown

When each of the four connecting lines and the regional station actually tie in, and at what offtake, is not in the 19 August note.

Sources

  1. Construction starts at Munga station Svenska kraftnät, 2026-08-19. Checked 2026-09-12.