Published 2026-09-12 · Event 2026-06-16

Svenska kraftnät’s Järpströmmen–Mörsil close-out is a 220 kV consult end, not reserved Jämtland hall power

Utility transformers and a web of overhead power lines against a clear sky.
Photo Alivia Alva on Unsplash

Svenska kraftnät’s 16 June 2026 Ismunden–Järpströmmen–Mörsil note says consultation on a changed concession for the existing 220 kV line between Järpströmmen and Mörsil has ended. A closed 220 kV window is not reserved offtake around Östersund.

Svenska kraftnät’s 16 June 2026 close-out note is the dated Järpströmmen–Mörsil source used here. It says the consultation on a changed network concession for the existing 220 kV line between Järpströmmen and Mörsil in Åre Municipality, open since the beginning of May, has ended. Comments will be compiled and answered in a consultation report that will form part of the concession application. A closed consult is not a reserved offtake.

The next-step sentence must stay a next-step sentence. After the consult, further studies will be made, the environmental-impact statement will be prepared and a final alignment will be chosen. Once the application for a changed concession has been filed and judged complete, the Energy Markets Inspectorate will run its own remittal. Those are process facts. They are not a hall agreement.

The sibling 400 kV sentence must stay a sibling sentence. The Ismunden–Järpströmmen–Mörsil hub writes a separate new 400 kV line between Järpströmmen and Ismunden, a new planned station in Bräcke Municipality, about 10 Swedish miles, with consultation in autumn/winter 2026, a concession filing in the winter of 2027/2028, construction start in 2030 and both stretches in service in 2035. The 16 June note does not close that 400 kV window. This article does not treat the 220 kV close-out as 400 kV progress.

Related grid notes stay on their own pages. Inlandspaketet’s complementary consult, Ramsele–Kilforsen and other SE2 rebuild notes are different dates and different legal rows. This article does not import an inland package or an Östersund campus name into a Järpströmmen–Mörsil close-out day.

DataCenterSweden records 16 June 2026 as a Svenska kraftnät 220 kV consult close-out for Järpströmmen–Mörsil. No project identifier is attached. The next update would need a later primary source that names a filed changed concession, a chosen 400 kV alignment or a reserved consumption agreement beside the corridor. Until then, the June close-out stays a 220 kV consult end — not reserved Jämtland hall capacity.

Why it matters

A Jämtland grid headline that also names a later 400 kV stretch is easy to file as spare Östersund hall power. The June note is usable only if the 220 kV close-out stays a close-out — not a reservation.

What remains unknown

The note does not file the changed 220 kV concession, open the 400 kV consult or name a reserved consumption agreement beside the corridor.