Published 2026-09-12 · Event 2025-05-12

Svenska kraftnät’s Horndal–Munga filing is a concession application, not reserved Mälaren hall power

Utility transformers and a web of overhead power lines against a clear sky.
Photo Alivia Alva on Unsplash

Svenska kraftnät’s 12 May 2025 Horndal–Munga note says a concession application for two new 400 kV lines between Avesta and Västerås was sent to the Energy Markets Inspectorate in April. A filing is not reserved offtake.

Svenska kraftnät’s 12 May 2025 filing note is the dated Horndal–Munga source used here. It says the concession application for the new lines was sent to the Energy Markets Inspectorate in April and that the inspectorate is now handling the case, including a remittal to concerned parties. A filing is not a reserved offtake.

The corridor sentence must stay a corridor sentence. The Horndal–Munga hub writes two new 400 kV alternating-current overhead lines between Horndal in Avesta Municipality and Munga in Västerås Municipality, about 63 km, plus a new station at Munga. Today’s double 220 kV line has reached the end of its technical life. The municipalities listed are Avesta, Sala and Västerås. Those are corridor facts. They are not a hall agreement.

The timetable sentence must stay a timetable sentence. The hub prints a concession application in 2025, construction start in 2030 and the new line in service in 2032. A separate December 2024 note says demolition of one of the two old lines between Horndal and Munga runs from January 2025 to 2028. Those are programme dates. They are not reserved megawatts.

Related grid notes stay on their own pages. The Munga-station construction-start note, Munga–Hamra, Bysingsberg–Munga, Fallviken–Horndal, Horndal–Avesta and the Horndal-station connecting-line note are different dates and different legal rows. This article does not import a station kickoff or a 220 kV rebuild into a Horndal–Munga filing day.

DataCenterSweden records 12 May 2025 as a Svenska kraftnät Horndal–Munga concession-filing notice. No project identifier is attached. The next update would need a later primary source that names a granted concession, a construction start or a reserved consumption agreement beside the corridor. Until then, the April filing stays an application — not reserved Mälaren hall capacity.

Why it matters

A 63-kilometre Avesta–Västerås headline that also names a new Munga station is easy to file as spare Mälaren hall power. The May note is usable only if the filing stays a filing — not a reservation.

What remains unknown

The note does not grant the concession, start construction of the new 400 kV lines or name a reserved consumption agreement beside Horndal–Munga.

Sources

  1. Svenska kraftnät applies for a permit for new power lines — Horndal–Munga Svenska kraftnät, 2025-05-12. Checked 2026-09-12.
  2. Horndal–Munga — Svenska kraftnät project hub Svenska kraftnät, 2025-05-12. Checked 2026-09-12.