Published 2026-09-12 · Event 2026-06-08
Bäsna–Repbäcken’s June filing is a second Dalarna 400 kV application, not reserved hall offtake

Svenska kraftnät’s Bäsna–Repbäcken hub, fetched with an 8 June 2026 filing note, says a concession application for a further 400 kV line between Gagnef and Borlänge has been sent to the Energy Markets Inspectorate. A filing is not reserved Dalarna hall power.
Svenska kraftnät’s Bäsna–Repbäcken hub, fetched with an 8 June 2026 filing note, is the dated rebuild source used here. The note says Svenska kraftnät has now submitted a network-concession application to the Energy Markets Inspectorate for a new 400 kV line between Bäsna in Gagnef Municipality and Repbäcken in Borlänge Municipality. A concession application is not a granted permit and not a reserved offtake.
The duty sentence must stay a duty sentence. The hub says a 400 kV overhead line already runs between the two stations and transfers electricity into Ellevio’s Dalarna grid. Svenska kraftnät plans a further line between the same stations to meet its connection duty toward the regional-network owner. An additional circuit for that duty is not a named campus agreement.
The timetable sentence must stay a timetable sentence. The hub table prints authority dialogue in 2024, consultation in 2025, the concession application in 2026, an Inspectorate concession decision in 2028, construction start in 2029/2030 and planned commissioning in 2031/2032. A 2 July 2026 note adds that ground investigations on a number of properties along the planned route are to start in late August. Those are rebuild dates. They are not reserved megawatts.
Named neighbouring papers stay neighbouring papers. Ellevio’s Dalarna snapshot, which already lists a later Svenska kraftnät Bäsna–Repbäcken row around 2032, EcoDataCenter’s Borlänge and Smedjebacken papers and the reserved-connection tables stay on their own files. This article does not import a hall reservation into a June filing.
DataCenterSweden records 8 June 2026 as a Svenska kraftnät concession filing for Bäsna–Repbäcken. No project identifier is attached. The next update would need a later primary source that names a granted concession, a construction start or a reserved consumption agreement beside the corridor. Until then, the second 400 kV line stays a Dalarna filing — not reserved hall capacity.
Why it matters
A second Dalarna 400 kV filing is easy to file as spare hall power beside Borlänge. The June application is usable only if the duty line stays a duty line.
What remains unknown
The hub does not print a granted concession, a reserved hall megawatt or a named datacentre applicant beside Bäsna–Repbäcken.
Sources
- Bäsna–Repbäcken — project hub (concession filing) — Svenska kraftnät, 2026-06-08. Checked 2026-09-12.